BORETE <br />E <br />A newly installed screw conveyor should run idle for 2 hours and run with load for 8 hours <br />before being put into use. Prior to commissioning, in addition to compliance of installation with <br />technical requirements, inspection shall be carried out on the following items: <br />The fasteners between connecting pieces shall be checked to ensure secure and safe connection. <br />They shall be subject to regular maintenance to prevent looseness; <br />The operating components shall be regularly lubricated to keep the lubricating oil in reduction <br />box above the minimum height of oil pointer; <br />The electrical signal and control device as well as their connection shall be checked to ensure <br />normal service; <br />Correct operation direction of bale breaking machine, belt conveyor, and discharging screw <br />belt after motor started up; <br />The following work should be conducted during commissioning: <br />Whether there is obvious noise at conveyor components; <br />Whether there is abnormal temperature rise at bearings; <br />Rotation and fastening of rollers and carrier rollers; <br />Tightness as to conveyor belt; <br />Sensitivity and reliability of buttons on electrical equipments; <br />Belt speed, no-load power and full -load power; <br />It should enter normal use if all going well where attention should be paid to: <br />Sundries and lastage are not allowed on conveying belt; <br />Do not stretch hands under the belt in operation; <br />Do not continue operation when deviation occurs until adjustment; <br />Realize the safe mark and location of the EmS before operation; <br />Check if the motor is overheating, Should shutdown to check problem if it was. <br />Note: Pay close attention to rotative flexibility of various transmission parts in the use of the <br />production line; analyze unusual sound and high temperature phenomena found in use and <br />36 <br />