Laserfiche WebLink
ATTACHMENT A <br /> SCHEDULE FOR GROUNDWATER INVESTIGATION <br /> PIONEER AMERICAS INC. <br /> 26700 S.BANTA ROAD,TRACY,CALIFORNIA <br /> ID Task Name Duration Start Finish July August September October November December <br /> 1 Off isite Property Access 40 days Mon 7/2/01 Fri 8/24/01 <br /> PF <br /> 2 Alvarez Propery 8 wks Mon 7/2/01 Fri 8/24/01 <br /> 3 Pombo Property 8 wks Mon 7/2/01 Fri 8/24/01 <br /> 4 Preliminary Field Activities 12 days Fri 8/24/01 Mon 9/10/01 <br /> 5 Schedule Drillers 1 day Fri 8/24/01 Fri 8/24/01 <br /> 6 Obtain soil boring permits 1 wk Mon 8/27/01 EFri8/31/01 <br /> 7 Update Health and Safety Plan 1 wk Mon 8/27/01 31/01 <br /> 8 Mark location in field 1 day Mon 9/3/01 Mon 9/3/01 <br /> 9 Utility clearance 1 wk Tue 9/4/01 Mon 9/10/01 <br /> 10 Monitoring Well Installation 2 wksETue 9/18/01 MoE10/8/01 <br /> 11 Well Development 1 wkTue 10/2/01 Mo <br /> 12 Sample Monitoring wells 2 days Tue 10/9/01 Wed 10/10/01 <br /> 13 Laboratory analysis 10 days Thu 10/11/01 Wed 10/24/01 <br /> 14 Receive laboratory results 0 days Wed 10/24/01 Wed 10/24/01 <br /> 15 Summary Report 37 days Tue 10/2101 Wed 11/21/01 <br /> 16 prepare draft summary report 6 wksET <br /> Tue 10/2/01 Mon 11/12/01 <br /> 17 submit draft to Pioneer for review 5 daysue 11/13/01 Mon 11/19/01 <br /> 18 prepare final report 2 days Tue 11/20/01 Wed 11/21/01 <br /> 19 submit final to RWQCB 0 days Wed 11/21/01 Wed 11/21/01 <br /> Task Rolled Up Task External Tasks 7a' <br /> Project:Pioneer Tracy Progress Rolled Up Milestone O Project Summary <br /> Date:Wed 6/6/01 Milestone . Rolled Up Progress <br /> Summary Split .„„����„�������� <br /> WORK PLAN 2001 Page 1 SECOR International Inc. <br />