4 <br /> Well Installation <br /> The fieldwork will require less than 1 week to complete This time frame includes the <br /> drilling of six boreholes and well installation The starting date will depend on County approval <br /> of the work plan and on driller availability <br /> Site Summary Report <br /> A summary report in letter form will be completed within approximately 6 weeks after field <br /> work is complete The report will include a description of field methods, results of laboratory <br /> analysis of soil samples, and conclusions The report will be submitted to ARCO for review, and <br /> the final report will be provided to the County and Regional Board for review <br /> SITE SAFETY AND HEALTH PLAN <br /> Specific health and safety procedures will be followed during the site work as outlined in <br /> BC's May 14, 1993, Site Safety and Health Plan {SSHP} prepared for this site The SSHP will <br /> be retained on-site during the field activities <br /> Use or disclosure of data contained on this sheet is subject to the restriction specified at the beginning of this <br /> document 15061REPORTS'1W0RKP1AN <br /> 01, <br />