Laserfiche WebLink
I15 October 2002 <br /> AGE-NC Project No 96-0232 <br /> IPage 7of19 <br /> I approximately 0 07 pounds of MTBE removed from MTBE-impacted ground water during this <br /> period(Appendix D) <br /> I The volume of extracted water between 27 August and 05 September 2002 was equal to 193,763 <br /> gallons, which equates to a mass of 1,615,402 pounds of processed water Multiplying the average <br /> MTBE concentration (assumed to be 9 4 gg/l based on the average of the 27 August and the 05 <br /> I September 2002 influent grab water samples) by the pounds of extracted MTBE-Impacted ground <br /> water yields approximately 0 02 pounds of MTBE removed from MTBE-Impacted ground water <br /> during this period (Appendix D) <br /> During the third quarter, an estimated 0 19 pounds of MTBE was extracted from ground water, to <br /> date, the ground water treatment system has removed a total of approximately 10 44 pounds of <br /> MTBE from extracted ground water(Table 8) Third quarter mass-volume calculations of MTBE- <br /> Impacted ground water extracted from the ground water pump-and-treat system are presented in <br /> Appendix D Plots of cumulative ground water pump and treat mass removal trends and Influent <br /> ground water MTBE concentrations versus time are in Appendix E <br /> 3.0. GROUND WATER MONITORING AND SAMPLING <br /> On 04, 05 and 06 September 2002, ground water monitoring and sampling were performed at 26 <br /> ground water monitoring wells (MW-1 through MW-13D), at ten ground water extraction wells <br /> (EW-1 through EW-10) and two San Joaquin County service area No 31 municipal water wells <br /> (CSA-1 and CSA-2) Ground water monitoring wells MW-10A, MW-12A and MW-13A were not <br /> sampled due to "dry" screen Intervals, ground water monitoring well MW-10B was not sampled <br /> because the sampling tube could not be inserted beyond 15 feet bsg Quarterly ground water <br /> monitoring procedures for the site were outlined in the AGE-prepared Work Plan Addendum, dated <br /> 28 January 1998, and approved by the SJCEHD by letter dated 24 February 1998 As-built <br /> monitoring well construction details are summarized In Table 9 <br /> IA coordinated effort was made with Three B's Truck Plaza (14749 Thornton Road, Lodi CA) to <br /> conduct ground water monitoring activities concurrently,the Three B's Truck Plaza tabulated ground <br /> water elevation results are In Appendix F <br /> 3 1 WELL MONITORING AND PURGE PROCEDURES <br /> On 04 September 2002, the depth to ground water was measured at each monitoring well from the <br /> top of each well casing to the nearest 0 01-foot utilizing a Solinst water level meter The ground <br /> . water elevation in each monitoring well was calculated by subtracting the measured depth to ground <br /> IAdvanced GeoEnvironrnental,Inc <br />