Laserfiche WebLink
Project Schedule(As Amended August 21, 1996) <br /> Stockton Former MGP Site <br /> Original <br /> Activity Schedule Scheduled Date' Date <br /> Submit Phase IV report 6 weeks after receipt of Phase IV analytical results N/A 6/10/96 <br /> Agency meeting to discuss and agree on Phase IV conclusions 2 weeks after submittal of Phase IV report N/A 6/24/96 <br /> PG&E response toPhase IV report comments 2 weeks after agency meeting N/A 7/8/96 <br /> Submit soil modeling report N/A 3/13196 <br /> Conference call to discuss soil modeling report N/A " 4/3/96 <br /> Complete treatability study and laboratory analysis N/A 4/17/96 <br /> Agency meeting to discuss groundwater objectives and goals, <br /> modeling results,and treatability study results N/A 5/22/96 <br /> Letter to agencies on soil and groundwater FS goals and <br /> approach 2 weeks after agency meeting N/A 6/5/96 <br /> PG&E/agency agreement on FS goals and approach Meeting at DTSC offices N/A 8/8/96 • <br /> Submit response to draft Soil OUTS comments N/A 8/19/96 <br /> Meeting to discuss and agree on VLEACH and source areas N/A 8/28/96 <br /> Submital of Work Plan for soil data collection and DI Wet test N/A 9/27/96 <br /> Agency approval of Work Plan for soil data collection 2 weeks after submittal of Work Plan N/A 10/11/96 <br /> Collect Area I soil data,Area H diesel info.,and conduct DI Wet N/A OctJ96 <br /> Meeting to discuss ARARs and screening of technologies N/A 9/12/96 <br /> Meeting to discuss and agree on screening of alternatives 6 weeks after agreement on VLEACH model and source areas and receipt of N/A 12/10/96 <br /> soil analytical results <br /> Submital of Work Plan for Zone B drilling on El Dorado Street N/A 11/12/96 <br /> Agency approval of Work Plan for Zone B drilling 2 weeks after submittal of Work Plan N/A 11/26/96 <br /> Drill and install well(s)in Zone B on El Dorado Street N/A DecJ96 <br /> Meeting to discuss and agree on detailed alternatives evaluation 4 weeks after agency mtg.and agreement on alternatives screening N/A 1!197 <br /> Delivery of draft FS report 6 weeks after agency agreement on detailed alternatives evaluation and N/A 2/18/97 <br /> results of El Dorado Street drilling <br /> Agency comments back 4 weeks after delivery of FS to agency N/A 3/18/97 <br /> Delivery of final FS report 4 weeks after receipt of agency comments N/A 4/15/97 <br /> Agency approval of FS report 2 weeks after receipt of final FS N/A 4/29/97 <br /> Delivery of agency draft RAP 12 weeks after approval of FS N/A 7/22/97 <br /> Agency comments back 4 weeks after delivery of RAP to agency N/A 8/19/97 <br /> Delivery of final draft RAP and draft Fact Sheet 4 weeks after receipt of agency comments N/A 9/16/97 <br /> Agencv aDDroval of draft RAP and draft Fact Sheet 2 weeks after receipt of final RAP and Fact Sheet N/A 9/30/97 <br /> Fact Sheet on RAP mailed 2 weeks after agency approval of draft RAP/Fact Sheet N/A 10/14/97 <br /> Public Notice/Comment period begins 2 weeks after Fact Sheet mailing N/A 10/28/97 <br /> Public Hearing Approximately 15 days after Public Notice N/A 11/12/97 <br /> Comments period ends 30 days after Public Notice N/A 11/27/97 <br /> DTSC and PG&E response to public comments and Final RAP 4 weeks after Comment period ends N/A 12/24/97 <br /> submittal to DTSC <br /> Notes: <br /> Shaded portions represent complete tasks <br /> 1.Based on approved schedule of August 23, 1993 <br /> 2.Based on actual completion dates or estimates as of August 21, 1996 <br />