Project Schedule(As Amended March 8, 1996) <br /> Stockton Former MGP Site <br /> Original Scheduled <br /> Activity Schedule Date' Date2 <br /> Fact Sheet on Soil RAP mailed 2 weeks after agency approval of draft RAP/Fact Sheet 5/22/95 12/23/96 <br /> Public Notice/Comment period begins 2 weeks after Fact Sheet mailed 5/22/95 1/6/97 <br /> Public hearing Approximately 15 days after Public Notice 6/5/95 1/21/97 <br /> Comments period ends 30 days after Public Notice 6/22/95 2/5/97 <br /> DTSC and PG&E response to public comments and Final Soil 4 weeks after comment period ends 7/20/95 3/5/97 <br /> RAP submittal to DTSC <br /> Ten months of groundwater level monitoring 4 weeks after completion of groundwater level monitoring N/A r' 3/95-12/95 <br /> Delivery of Phase IV Work Plan 2 weeks after submittal of Phase IV Work Plan N/A 1/8/96 <br /> Agency meeting to discuss comments on Work Plan 2 weeks after agency meeting N/A 1/22/96 <br /> Delivery of final Phase IV Work Plan 1 week after submittal of final Phase IV Work Plan N/A 2/5/96 <br /> A ency approval of final Phase IV Work Plan NIA 2/22/96 <br /> Obtain site access 2 weeks after agency approval of final Phase IV Work Plan N/A 3/14/96 <br /> Start Phase IV fieldwork 2 weeks after site access obtained N/A 3/18/96 <br /> Complete Phase IV fieldwork 6 weeks after Phase IV start date N/A 4/29/96 <br /> Submit Technical Memorandum 6 weeks after receipt of Phase IV analytical results N/A 6/10/96 <br /> Agency meeting to discuss Phase IV Technical Memorandum 2 weeks after submittal of Memorandum N/A 6/24/96 <br /> and Feasibility Study <br /> PG&E response to Technical Memorandum comments 2 weeks after agency meeting N/A 7/8/96 <br /> Delivery of draft groundwater FS report 6 weeks after PG&E response to Agency on Phase IV Memorandum N/A 8/19/96 <br /> Agency comments back 4 weeks after delivery of FS to agency N/A 9/16/96 <br /> Delivery of final Groundwater FS report 4 weeks after receipt of agency comments N/A 10/14/96 <br /> Agency approval of Groundwater FS report 2 weeks after receipt of final FS N/A 10/28/96 <br /> Delivery of agency draft Groundwater RAP 12 weeks after approval of FS N/A 1/20/97 <br /> Agency comments back 4 weeks after delivery of RAP to agency N/A 2/17/97 <br /> Delivery of final draft Groundwater RAP and draft Fact Sheet 4 weeks after receipt of agency comments N/A 3/17/97 <br /> A en a royal of draft Groundwater RAP and draft Fact Sheet 2 weeks after receipt of final RAP and Fact Sheet N/A 3/31/97 <br /> Fact Sheet on Groundwater RAP mailed 2 weeks after agency approval of draft RAP/Fact Sheet N/A 4/14/97 <br /> Public Notice/Comment period begins 2 weeks after agency approval of RAP/Fact Sheet N/A 4/28/97 <br /> Public Hearing Approximately 15 days after Public Notice N/A 5/13/97 <br /> Comments period ends 30 days after Public Notice N/A 5/28/97 <br /> DTSC and PG&E response to public comments and Final 4 weeks after Comment period ends N/A 6/25/97 <br /> Groundwater RAP submittal to DTSC <br /> 1. Based on approved schedule of August 23, 1993 2. Based on actual completion dates or estimates as of March 8,1996 <br />