Monitoring Well Destruction Work Plan <br /> Raymond Investment Corporation <br /> November 20,2012 <br /> Page 5 <br /> 6.0 PROJECT SCHEDULE <br /> Work can commence upon approval of this work plan by the SJCEHD and notification by the client to <br /> proceed. The field portion of the investigation can be'completed within approximately eight weeks after <br /> the necessary permits are received. A report can be submitted to the SJCEHD within four weeks of the <br /> completion of the fieldwork. If you need additional information or have any questions, please call Bill <br /> Cook at(209) 234-0518. <br /> Respectfully submitted, <br /> Ind <br /> CONDOR EARTH TECHNOLOGIES, INC. <br /> A L GE <br /> o <br /> t� BILL A. COOK Ili <br /> Bill A. Cook III, PG, C. No. 2534 Casey Kipf, PG <br /> Associate Geologist CERTIFIED Senior Geologist <br /> ENGINEERING <br /> GEOLOGIST <br /> Or C A\-N <br /> P;13000_prj0949 Raymond Investment Beverly Garcia13849Q Well Destruction WP and Close-out\Reportslwork planslWP 20121120_3849Q Monitoring Well <br /> Destniction Work Plan.docx <br /> Irk <br /> is CONDOR <br />