Workplan for Supplemental Investigation <br /> 2005 Navy Drive, Stockton, CA <br /> January 2, 2013 <br /> Page 11 of 12 <br /> 4.0 Proposed Schedule <br /> Grab Groundwater Permit Application will be obtained within 20 days after Workplan <br /> approval by the RWQCB. <br /> Utility Clearance: 10 days after permits obtained <br /> Soil Gas Sampling: 30 days after permits obtained <br /> Grab Groundwater Sampling: 60 days after permit obtained <br /> Investigation Report: 45 days after all sampling results are obtained <br /> from laboratory <br /> These timelines are subject to drill rig and subcontractor availability and approval of <br /> all necessary permits and approvals but are not expected to deviate much based on <br /> current schedules and availability. <br /> Risk-Based Decisions, Inc. <br />