Laserfiche WebLink
March 18, 1993 <br /> Page 10 <br /> Implementation Schedule <br /> Upon approval of the recommended strategy by Unocal, PACIFIC will submit a <br /> scope of work and fee estimate to initiate remediation. A remediation schedule is <br /> presented below. <br /> Task Completion Date <br /> Remedial strategy approval 04/19/93 <br /> Submit air emissions permit apprica6on 05/14/93 <br /> Complete design of remedial system 06/18/93 <br /> Obtain building permits 07/09/93 <br /> Prepare bid package 07/16/93 <br /> Purchase capital equipment 08/13/93 <br /> Construction of remedial system 08/27/93 <br /> System start-up 10/08/93 <br /> Implementation will follow this schedule,given unforeseen circumstances do not <br /> hinder the pace of implementation. If problems meeting the proposed schedule <br /> arise, it will be revised, and the appropriate parties will be contacted. <br /> If you have any questions, please call. <br /> Sincerely, <br /> Pacific Environmental Group, Inc. <br /> Brian Frus <br /> Senior Staff <br /> ^jEngineer <br /> Lance D. Geselbracht, P.E. <br /> Senior Engineer <br /> RCE 34688 <br /> 3100104/IRAP - <br />