5. Place the panels. Position the panels on the prepared subgrade with geotextile <br /> face down. Cutto shape with skill saw with fine-toothed blade (in reverse position). <br /> Use protective gloves to avoid abrasions. Top of cell panels should be 1 cm (10 mm) <br /> below adjacent hard surfaced pavements or final grade. <br /> 6.All hard surfaces abutting areas to receive Gravel Surfacing shall be in place prior to <br /> commencing work. Finished gravel work should be no more than 1/2" below adjacent <br /> hard surfaces. <br /> 7. Place first row of panels against a stationary edge if possible. The panels have <br /> interlocking connectors. You can install panels 'side by side' or in a 'herring bone" <br /> pattern; either method works. No anchors are needed for gravel stabilizer panels <br /> installed on slopes less than 20 degrees. <br /> 8. Fill cells with chosen infill. Maximum particle size of granular infill material should not <br /> exceed'/z'. Minimum particle size can be 1/8"to allow porosity.Cell walls must be <br /> sufficiently covered with infill to prevent any equipment or load bearing vehicular traffic <br /> from damaging the grid. <br /> 9. Install edge restraint if desired. Standard metal, plastic, concrete edge <br /> restraints orconcrete curbing may be used. <br /> 10. You can: Water stones thoroughly for an immediate finished look! <br /> Post-Placement <br /> A. Reserve a few 5 g. buckets of infill stones on site to top dress as necessary over <br /> the next year. Once the area is fully packed, top dressing is no longer necessary. <br /> B. Snow plowing — Use shovels or blades with plastic blades. If using a metal blade, <br /> set blade 2" above gravel surface, leaving a layer of snow. This system is free <br /> draining during freeze/thaw events. <br /> C. Use of salt for de-icing is allowed. <br />