My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
ARCHIVED REPORTS XR0011108
EnvironmentalHealth
>
EHD Program Facility Records by Street Name
>
E
>
ESCALON
>
1329
>
3500 - Local Oversight Program
>
PR0544806
>
ARCHIVED REPORTS XR0011108
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
9/5/2019 8:57:32 AM
Creation date
9/5/2019 8:38:04 AM
Metadata
Fields
Template:
EHD - Public
ProgramCode
3500 - Local Oversight Program
File Section
ARCHIVED REPORTS
FileName_PostFix
XR0011108
RECORD_ID
PR0544806
PE
3528
FACILITY_ID
FA0000293
FACILITY_NAME
Pershing Holdings, Inc. DBA Esclon Arco
STREET_NUMBER
1329
STREET_NAME
ESCALON
STREET_TYPE
Ave
City
Escalon
Zip
95320
APN
22510003
CURRENT_STATUS
02
SITE_LOCATION
1329 Escalon Ave
P_LOCATION
06
P_DISTRICT
004
QC Status
Approved
Scanner
SJGOV\wng
Tags
EHD - Public
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
30
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
... Geolagica(Technics 2nc. Page 2 <br /> Pitot Test Report <br /> COE-Arco <br /> Project No.750.2 <br /> August 8,2000 <br /> 2.0 SUMMARY OF WELL .INSTALLATION <br /> In accordance with the approved work plan and for the purpose of determining if the site is <br /> conducive to vapor extraction as a remedial alternative, Geological Technics Inc. drilled and <br /> installed four vapor extraction wells according to the following schedule: <br /> '-r • VEW-1 and VEW-2 were drilled on April 29, 1999. <br /> • VEW-3 and VEW-4 were installed on July 30, 1999. <br /> ,.. The four (4) soil borings were drilled (2 to a depth of 55 feet and 2 to a depth of 27 feet) and <br /> converted into vapor extraction wells. The borings, VEW-1 and VEW-2 were drilled at the <br /> eastern edge of the site, under the former sidewalk along the old Escalon/Bellota Road. The <br /> borings for VEW-3 and VEW-4 were drilled in the northern part of the excavation, adjacent <br /> to the northern dispenser island (Figure 2, Site Map). <br /> The vapor extraction wells were constructed using 4-inch diameter PVC casing with flush <br /> +� threads. The table below shows the construction details. <br /> Well o. Dia./Tl) creep Slot Filter Pack Trans. Grout Scal <br /> �.. _ Seal <br /> VhW-_T___T755"___ - 0- <br /> _� 4"T27T -—10-27, ea gravel $.5_-7 -6.54�' 0-6.5' <br /> ea grave <br /> _ <br /> _4' - _l-" ea gravel-10- <br /> A surface seal was achieved by pumping a neat cement grout via a tremie tube {augmented <br /> with <4% bentonite) from the top of the Transition Seal to within 5 feet of the ground <br /> surface. The wells were cut off five feet below ground surface, capped, covered with steel <br /> plates and buried with dirt. This was done to allow the road, sidewalk and other <br /> +... improvements to be completed without damaging the wells. <br /> Soil samples collected from VEW-1 showed only the presence of low levels of Xylene and <br /> �. MTBE. Low to moderate levels of BTEX, TPH-G and MTBE were detected in the soil <br /> samples from MW-1, which is adjacent to VEW-3 & VEW-4. Soil analytical data is <br /> included in Table 1 of Appendix A. <br /> On June 27, 1999, GTI and Del Tech personnel used a backhoe to expose the tops of the two <br /> vapor extraction wells, VEW-I &VEW-2. The new Escalon/Bellota Road now covers these <br /> two vapor extraction wells. A trench was dug at approximately 4 feet below grade, heading <br /> to the west from the vapor wells. Conveyance piping was laid in the trench and VEW-1 & <br /> VEW-2 were hooked to it. The conveyance piping was stubbed off at approximately 3 feet <br /> below ground surface at the location of MW-1, VEW-3 and VEW-4. The trench was <br /> backfilled and compacted. <br /> On April 12, 2000, the work to bring all of the wells to surface grade and enclose them inside <br /> utility boxes was completed at the site. <br /> A full discussion of the well installation and soil testing is included in the Additional Site <br /> Characterization Report submitted by GTI on January 31, 2000. <br />
The URL can be used to link to this page
Your browser does not support the video tag.