Laserfiche WebLink
Ker;Sullivan -2- <br /> COMMENTS ON DEVELOPMENT <br /> QX-01-02 <br /> All private roads involved in an excavation shall be maintained so as to control the dust. <br /> C b'. A video tape of the planned haul routes showing conditions of all San Joaquin County roads shall be <br /> submitted to the Department of Public Works. The condition of County maintained roads along the haul <br /> route shall be reviewed by the Department of Public Works prior to the start of excavation. <br /> (Development Title 9-1415.2) <br /> Loads on all public roads shall be limited to legal loads only. <br /> (Vehicle Code Section 35551) <br /> An encroachment permit shall be required for work within Public road rights-of-way . <br /> (Development Title Sections 9-1145.4 and 9-1145.5) <br /> {, A haul route shall be approved by Department of Public Works from project site to State Highway. The <br /> portion of Blewett Road east of Koster Road and Koster Road north of Blewett Road shall not be <br /> considered as the haul route for the project. An Engineering Study of County roadway used as haul <br /> routes shall be required. The Engineering study shall determine; the adequacy of roadway width <br /> requirements, structural section, R-value, Traffic index, overall safety and shoulder requirements. The <br /> study shall be based on cumulative traffic generation of existing and future mining operations in the <br /> Vernalis area. The report shall also recommend improvements required to county roads to mitigate the <br /> increased truck traffic to comply with the county level of service standards on roadways and intersections. <br /> The applicant shall be required to do all mitigations required by the Engineering Study. <br /> rq 7 A security bond or other instrument in the amount and form acceptable to the Department of Public <br /> Works shall be deposited with the Department. The bond will guarantee that if the permittee fails, <br /> refuses or neglects to repair, under permit any damages to any County roads along the haul route resulting <br /> from permittee's operation, the Department of Public Works may use the funds to restore County roads to <br /> equal or better than original condition. The amount of deposit or security required may be adjusted at the <br /> discretion of the Director of Public Works. The cash deposit or security shall be replenished or adjusted <br /> following any payment to the County for work performed, or to provide for additional future work that <br /> may be required. <br /> (Development Title 9-854.3) <br /> A Maintenance Agreement to ensure that Koster Road(including all bridges on haul route), Blewett Road <br /> and any other County roads utilized as a haul route is maintained to a condition acceptable to San Joaquin <br /> County shall be executed by the applicant. The Maintenance Agreement shall remain in force for the <br /> duration of operation under this permit. <br /> L V. The Traffic Impact Mitigation Fee shall be required for this development. The fee is due and payable at <br /> the time of grading permit application. The fee currently is$ 184.54 per trip-end in the Tracy area. The <br /> fee shall be automatically adjusted July I of each year by the Engineering Construction Cost Index as <br /> published by the Engineering News Record. The number of trip-ends may be determined by a proportion <br /> to the length in time of the excavation operation. (Resolutions R-00-433) <br />