ti <br /> Revisions of Approved Actions: Conditions la and im of Quarry Excavation Permit PA-02-370 <br /> Bellino Pit <br /> Operator—George Reed, Inc. <br /> Modify phasing timeline provisions and extend the life of permit. <br /> Due to low market demand for construction aggregates over the past few years,George Reed, Inc. (GRI) <br /> is requesting an extension of its 12-year Quarry Excavation permit scheduled to expire in 2015, to 25 <br /> years, to expire in 2028. Reclamation of each mining phase would occur and be completed within 2 <br /> years of the cessation of excavation activity in that particular phase, in accordance with Development <br /> Title 1415.3[0], and Condition 1.1. Final reclamation of the last phase would be completed by 2030. <br /> Proposed revision to the Conditional language is as follows: <br /> Condition l.a. (proposed revision) <br /> "This is a Quarry Excavation application to remove approximately 2.4 million cubic yards of rock, sand, <br /> and gravel from approximately 71 acres of an 80-acre site over a -year period. The mining will <br /> occur in three phases as described and presented in the Mining and Reclamation Plan. Pose 1shall <br /> a.. ... il3 1... . �h'...,.,1 L..,enno ol.�.., �ti-,il-EE3r ,tc�cn-vrz-.F c-vv.c., j^ _7 2�-1-1- <br /> ^h 1-sh,R'l Ge^5'5t of 26 @UeS be FeeiatmR4-by-2494-S—The material that is excavated shall be <br /> transported approximately 0.10 miles southwest via a conveyo River Road to an existing <br /> processing facility` .,,I by Condition Of Approval N(, ' . Reclamation is proposed to be <br /> continuous and concurrent with mining. The quarry shall be replanted in either walnuts or almonds in <br /> 15-to 30-acre increments." <br /> Condition l.m. <br /> TIME LIMITATION: The Quarry Excavation permit shall remain in effect as long as the excavation <br /> continues in compliance with the approved Permit (Development Title Section 9—1415.6 [p]) and <br /> i-,Wun II.b (Estinated Production Schedule) of the Reclamation Plan, or as wherwise exiencled through <br /> submittal and approval of an Interim Management Plan (per Section 2770(h) of California SMARA <br /> Statute and Regulations]. <br /> Phase 1 LxcavatieR Fall b completed by 2007 Rd Feclamati,. ;Loll be P pleted b 2009. <br />