Laserfiche WebLink
ft <br />. F <br />N otes <br />i <br />i <br />Estimates for capital costs for initial Iron Sponge system purchase and installation are based on estimates obtained from <br />, A MVLLC Company from their experience with the iron Sponge technology. <br />2 The design, permitting, and startup costs for the catalyst systems were estimates made by SCS Engineers from recent experience. <br />�' <br />a Applied at 8.75% rate for major equipment purchases <br />4 A 10% contingency was applied and considered reasonable for the uncertainties with this project <br />5 MVLLC estimate assuming $0.1511b cleanout and SCS estimates $3501ton or $0.211b disposal cost as hazardous waste. <br />B SCS estimate based on $25,100 per changeout. Cost includes 3 trucks at $7,5001load, 2 men at $50/hr for 8 hours each, <br />and a crane rental for $1,800/day including increased transportation costs to hazardous waste site <br />s 7 SCS estimate 5% of capital costs <br />a f a SCS estimates 2.5 kW required at $0.11 kW -hr for a full year (8,760 hours) <br />