Laserfiche WebLink
left the site at 12:00 was back on site to observe the majority of the <br /> abandonment operation of MW-1. The inspector left the site shortly after <br /> ' 15:00. <br /> The Halliburton field engineer arrived back on site at approximately 15:00 <br /> with the overshot tool and sub (see photograph #6, Figure 3). The overshot <br /> tool and sub were connected to the drill stem which, in turn, was lowered <br /> through the rod chuck and into the casing of MW-2. The overshot tool was <br /> positioned over the section of rod inside the casing and then pushed on, <br /> hydraulically, with the drill rig ram. The successful recovery of the drill stem <br /> is shown in photograph #7, Figure 3. After recovery of the drill stem, the jet <br /> ' bit and sub were removed, the broken section of stem replaced, and <br /> additional drill stem sections added in order to position the open-end rod at <br /> 35 feet below the top of the well casing. The partially set grout was then <br /> washed out to 35 feet using potable water under pressure. The drill stem was <br /> then pulled and the jet bit and sub were connected. The twin-bin dry grout <br /> mix truck was dispatched to Woodland shortly after 15:00 to re-supply. The <br /> BSK and Halliburton personnel left the site and locked the gates at 17:30. <br /> Photograph #8, Figure 3 shows the jet bit and sub and the erosion of the <br /> section near the jet nozzle after the first day of use. <br /> 3.2 June 2 Activities - The BSK and Halliburton personnel were on site at 07:45 <br /> ' along with the new supply of dry grout mix. Difficulties experienced in the <br /> operation from the previous day were discussed along with general safety <br /> issues until 08:15. At 08:15, the drill stem with the jet bit and sub attached <br /> was lowered to 35 feet where a perforation operation was conducted. The <br /> remainder of the perforations were completed at the intervals proposed in the <br /> Work Plan. Halliburton's Compupac (data acquisition system) was not <br /> ' functioning due to a faulty pressure sensor on the RCM® panel. After <br /> observing a very low viscous return grout mixture, BSK's field supervisor and <br /> project manager questioned Halliburton's field supervisor about this condition. <br /> ' The Halliburton field supervisor stated that the grout mix on the previous day <br /> had contained two percent by weight of bentonite gel, but the mix used on <br /> this day was the original 50:50 cement/Pozmix® A mix proposed in the Work <br /> Plan. Also observed in the overflow return was a black colored residue which <br /> floated on the free bleed water. The weight of the return grout was <br /> determined to be 13.7 pounds per gallon using a Mud Scale. The <br /> abandonment operations on MW-2 were completed at 09:15. The SJPHS <br /> inspector was not on site during the jet grouting operations for MW-2. Two <br /> containment pools were used to allow the overflow grout mixture to solidify. <br /> The set up was started over MW-3 at 9:40 and completed at 10:05. The <br /> Halliburton field engineer indicated that the problem with the pressure sensor <br /> had been solved and the Compupac would be recording pressure, density, and <br /> rate on this well (see photograph #9, Figure 4). As previously discussed in <br /> Section 2.2, the jet grouting procedure was modified to eliminate the bottom <br /> ' perforation. The drill stem with the jet bit and sub attached was lowered into <br /> 5 <br /> &Associates <br />