Work Plan for Soil Excavation 3 <br /> The Southland Co Store#20304 455 Grant Line Road CA Janua 26 1998 <br /> The document will be reviewed and signed by all Fluor Daniel GTI personnel and subcontractors <br /> performing work at the site <br /> An excavation permit will be applied for,if needed,through the SJCPHS prior to conducting the on-site <br /> activities In addition,the Stockton Fre Department will be notified of the activity,so that personnel can be <br /> onsite to witness the excavation,if necessary <br /> TASK 2. SCOPE OF WORK <br /> Pre-Excavation Activities <br /> Subsurface utilities well be located and marked pnor to conducting subsurface activities Temporary <br /> fencing will be put up along the southern side of the store at the sidewalk,the property line on Buthman <br /> Avenue,and Grant Line Road to prevent pedestrian traffic from entering the excavation area (Figure 2) <br /> Shoring of the excavation walls will not be required given the shallow depth of impacted sod, and the silty <br /> clay stratigraphy from 0 to 5 feet BGS, below the 4-inch-thick asphalt cap Groundwater is expected at <br /> approximately 5 feet BGS A vacuum truck company will be contracted to evacuate,transport and dispose <br /> of the exposed groundwater during the excavation Groundwater recharge has been estimated at greater <br /> than 20 gallons per minute Fourth quarter groundwater sample analytical results well be used for <br /> characterization of the water prior to treatment and disposal <br /> Soil Excavation and Sampling <br /> Fluor Daniel GTI personnel will supervise the excavation of sod in areas that have historically contained <br /> elevated concentrations of petroleum hydrocarbons The expected area of highest concentration In soil <br /> will be excavated as shown on Figure 2 The estimated size of the main source area is based on data <br /> collected during past soil and groundwater assessment and historical groundwater mondonng sampling <br /> Sod samples at the lateral and vertical limits of the excavation will be collected in 2-Inch-diameter by 6- <br /> inch-long brass tubes directly from the bucket of the excavator All samples will be capped,labeled, <br /> placed on Ice,and transported under chain-of-custody to a state-certified laboratory for analysts of <br /> benzene,toluene,ethylbenzene and xylenes(BTEX),total petroleum hydrocarbons-asgasollne(TPH-G) <br /> by Environmental Protection Agency(EPA) methods 8020/8015 modified,and oxygenates methyl-tert <br /> butyl-ether(MTBE),tert butanol (TBA),d0sopropyl ether(DIPS),ethyl-tert-butyl-ether(ETBE),and tart <br /> amyl-methyl-ether(TAME) by EPA method 8260 <br /> Field phototonization detector(PID) readings of soil vapors will be recorded to document the relative <br /> hydrocarbon content of the soil during excavation as a qualitative method for determination of the limits of <br /> excavation The final lateral extent and depth of the excavation will be measured and sketched on a site <br /> 045~LTR SOUTHLAND <br /> FLUOR DANIEL GTI <br />