ACTIVfrY-ALTERNATIVE A 2 Range-Low Range-High
<br /> PLANNING AND PREPARATION
<br /> Stortnwater Permit NIA NIA
<br /> SurVeymg NIA NIA
<br /> Workplan $3,50000 $5,000
<br /> ' INSTALL DEWATERING/TREATMENT SYSTEM
<br /> Discharge fee $3,00000 $3,50000
<br /> ' System design $1,00000 $2,00000
<br /> USA-utility locates $30000 $50000
<br /> ' Install piping,instrumentation(flow meter,LEL meter) $7,00000 $9,00000
<br /> Dewatering pumps/transfer pumps(set power) $5,000,00 $6,00000
<br /> Holding tanks $1,50000 $3,00000
<br /> Carbon system(based on a 1-month rental fee) $3,50000 $5,00000
<br /> Lab analysis for discharge $2,50000 $3,50000
<br /> ' System demob/spent carbon recycling $3,00000 $5,00000
<br /> EXCAVATION AND BACKFILLING
<br /> Stormwater controls $1,00000 $2,00000
<br /> Design shoring Included Below
<br /> Remove/dispose concrete slab $1,00000 $2,00000
<br /> Destruction of monitoring well $2,00000 $3,00000
<br /> Remove power line and power pole $2,00000 $2,50000
<br /> ' Soil waste profile $2,00000 $2,50000
<br /> Excavation of soil/backfilling/transportation of impacted soil $69,94615 $75,49744
<br /> ' Addition of Calcium Peroxide f 1,000 hounds) ;O $3,40000 $3,40000
<br /> Disposal of impacted soil $22,20513 $26,64615
<br /> ' Soil sampling/analysis $5,50000 $8,00000
<br /> Project oversight $7,00000 $9,00000
<br /> Compaction testing $2,50000 $3,50000
<br /> Replace power pole $2,00000 $2,50000
<br /> &45,000() mow 0
<br /> ' TOTAL BUDGET COST ESTTMATE
<br /> $150,85128 $183,04359
<br /> ALTERNATIVE A 2(With dewatering and no shoring)
<br /> R ICONTGRAMStockton\CAPICap Addendum Costs &Supporting Calcs
<br /> 1