Laserfiche WebLink
• <br /> ALTERNATIVE 6 GF-CMATRIX <br /> COMPLETE EXCAVATION FOR ONSITE LOW-TEMPERATURE THERMAL DESORPTION <br /> • PRELIMINARY COST ESTIMATE <br /> Former ContiGroup Grain Elevator Page 3 of 3 <br /> 1805 Harbor Street <br /> Stockton,California <br /> TASK <br /> ACTIVITY QUANTITY UNIT UNIT$ COST$ SUBTOTAL$ <br /> ' RECONSTRUCTION <br /> field activates 280,000 <br /> railroad rebuild 300 LF 1 lump sum 250,000 250,000 <br /> ' replace 4,500-ft asphalt pavement 1 lump sum 15,000 15,000 <br /> fencing 200 LF 25 5,000 <br /> replace utility pole and power line 1 lump sum 10,000 10,000 <br /> RECONSTRUCTION SUBTOTAL ,S 280,000 <br /> 15%project management cost 0 15 3,683,000 552,500 <br /> 20%contingency cost 02 3,683,000 920,800 <br /> TOTAL $ 5,156,300 <br /> 1 <br /> 1 <br /> 1' <br /> I 11:)oc_Safei9000s199634CAP5AppB Alternatives As 1016/20049 52 AM <br />