| '    						•       	ALTERNATIVE 7
<br />     						COMPLETE EXCAVATION FOR OFFSITE DISPOSAL    		GEOMATRIX
<br />  '     							PRELIMINARY COST ESTIMATE
<br />     								Former ConttGroup Grain Elevator
<br />       									1805 Harbor Street    						Page 2 of 2
<br />      									Stockton California
<br />      																		TASK
<br />		ACTIVITY   							QUANTITY   UNIT     UNIT$     COST$      SUBTOTAL$
<br />		DEWATERING and TREATMENT SYSTEM(cont'd)
<br />		Other mist       															110,000
<br />		treatment system installation,startup,operations     			60  	day  	1,500	90,000
<br />  '   	laboratory analysts of discharge water samples       			8   	ea     	500 	4,000
<br />		system decommissioning     						1	lump sum      10,000	10,000
<br />		spent GAC pickup and disposal      					I	lump sum       6 000 	6,000
<br />		DEWATERING and TREATMENT SYSTEM SUBTOTAL   								S  	191,000
<br />		DEMOLITION
<br />		field activities    															116,000
<br />		fence									2       lump sum       4,000 	8 000
<br />  '   	decommison existing monitoring wells       				4       lump sum       5,000	20,000
<br />		railroad demolition  							I	lump sum      50,000	50,000
<br />		remove 4 500-ft2 asphalt&recycle   					I	lump sum      20,000	20,000
<br />		remove overhead powerline and pole 					I	lump sum       8,000 	8,000
<br />		remove concrete slab&recycle      					I	lump sum      10,000	10,000
<br />		DEMOLITION SUBTOTAL  												S  	116,000
<br />		EXCA VA TION and BACKFILL
<br />		pre-veld activities 															50,000
<br />		pre-profile soil waste 							1	lump sum       5,000 	5,000
<br />		stormwater controls installed 						1	lump sum      10,000	10,000
<br />  '.    Utility survey&potholing   						1	lump sum       5,000 	5,000
<br />		design shonng       							1	lump sum      15,000	15,000
<br />		implement utility protection plan     					1	lump sum      15,000	15,000
<br />		excavation      															1,414,200
<br />  '  	mob/demob  								1	lump sum      15,000	15,000
<br />		install&remove shoring     						1	lump sum    300,000       300,000
<br />		excavate 4,200 cy overburden soil and stockpile    			4200     cubic yard  	12	50,400
<br />  '  	excavate 8,400 cy affected soil     					8400     cubic yard  	15       126,000
<br />		offsite transportation and disposal of affected soil  			14200	ton      	40       568,000
<br />		locate and test source of backfill soil 					1	lump sum      10,000	10,000
<br />		sample and test stockpiled overburden soil   				42  	ea     	250	10,500
<br />  '  	move,place and compact overburden soil  				4200     cubic yard   	9	37,800
<br />		import fill purchase,transport,place,compact     			14200	ton     	20      284,000
<br />		import baserock purchase,transport,place,compact       		500 	ton      	25	12,500
<br />		Other mtsc																45,000
<br />  '  	field work oversight and coordination       				40 	days  	1,000	40,000
<br />		mist field equipment							1	lump sum       5,000 	5,000
<br />		EXCAVATION and BACKFILL SUBTOTAL										$	1,509,200
<br />   '  	RECONSTRUCTION
<br />		field activities    															280,000
<br />		railroad rebuild 300 LF      						1	lump sum    250,000       250,000
<br />  '  	replace 4500-ft asphalt pavement     					1	lump sum      15,000	15,000
<br />		fencing    								200  	LF      	25 	5,000
<br />		replace utility pole and powerltne    					I	lump sum      10,000	10,000
<br />		RECONSTRUCTIONSUBTOTAL   											$  	280,000
<br />      																		TASK
<br />      b 	ACTIVITY   							QUANTITY   UNIT     UNIT$     COST$       SUBTOTAL$
<br />       •   15%protect management cost      					0 15  				2,231,200      	334,700
<br />		20%contingency cost       						02  				2,231,200      	557,800$	3,123,700