ACTIVITY-ALTERNATIVE A 2 _ ___ Range-Low Range-High
<br /> PLANNING AND PREPARATION
<br /> Stormwater Permit N/A N/A
<br /> Surveying N/A N/A
<br /> Workplan $3,500.00 $5,000
<br /> INSTALL DEWATERINGrTREATMENT SYSTEM
<br /> Discharge fee $3,000.00 $3,500.00
<br /> System design $1,000.00 $2,000.00
<br /> USA-utility locates 5300.00 $500.00
<br /> Install piping,instrumentation(flow meter,LEL meter) $7,000.00 59,000.00
<br /> Dewatering pumps/transfer pumps(set power) $5,000,00 $6,000.00
<br /> Holding tanks $1,500.00 $3,000.00
<br /> Carbon system(based on a 1-month rental fee) $3,500.00 55,000.00
<br /> Lab analysis for discharge $2,500.00 $3„500.00
<br /> System demob/spent carbon recycling $3,000.00 $5,000.00
<br /> EXCAVATION AND BACKF LLING
<br /> Stormwater controls $1,000.00 $2,000.00
<br /> Design shoring Included Below
<br /> Remove/dispose concrete slab $1,000.00 $2,000.00
<br /> Destruction of monitoring well $2,000.00 $3,000.00
<br /> Remove power line and power pole $2,000.00 $2,500.00
<br /> Soil waste profile $2,000.00 $2,500.00
<br /> Excavation of soil/backfilling/transportation of impacted soil $69,946,15 $75,497.44
<br /> Addition of Calcium Peroxide(1,000 pounds) $3,400.00 $3,400.00
<br /> Disposal of impacted soil $22,205.13 $26,646.15
<br /> Soil sampling/analysis $5,500.00 $8,000.00
<br /> Project oversight $7,000.00 $9,000.00
<br /> Compaction testing $2,500.00 $3,500.00
<br /> Replace power pole $2,000.00 $2,500.00
<br /> ShGAHOWWFing plaemm $45,000. $50,4W.
<br /> TOTAL BUDGET COST ESTIMATE
<br /> $150,851.28 $183,043.59
<br /> ALTERNATIVE A 2(With dewatering and no shoring)
<br /> R:ICONTGRAN1StocktonlCAPICap Addendum Costs&Supporting Caics