Ms.Vicki McCartney,SJCEHD August 29,2008 <br /> Work Plan for Bench-Scale Test and Injection Well Installation Project No.2046-3250-01 <br /> Parkinson's I-5 ARCO Service Station,Stockton,California <br /> Page 6 <br /> testing, the extent of the effects and the time required to reverse the effects (via attenuation) will <br /> be estimated during the bench-scale testing. <br /> To facilitate bench-scale testing, the collection of soil and groundwater samples is required. <br /> Since a drilling event will be required to obtain the required soil samples for a bench-scale test, it <br /> will be most cost-effective to use this drilling event to also install two 03 injection wells for use <br /> during the pilot-scale phase of work. Therefore, Stratus proposes to advance two soil borings <br /> and install dedicated 03 injection wells within the resultant boreholes (IW-1 and IW-2; Figure 2). <br /> The locations of the proposed wells were selected to target 03 injection in the areas east of the <br /> fuel-dispensers (MTBE and TBA plumes) and south of the USTs (MTBE plume). In addition, <br /> the locations of the proposed injection points are strategically located to allow for the use of <br /> existing monitoring wells as observation wells during the pilot-scale testing. A work plan <br /> detailing the pilot-scale testing procedures and protocols will be prepared and submitted to <br /> SJCEHD under separate cover, once the bench-scale testing is complete. Details associated with <br /> bench-scale testing and soil boring/well installations are discussed in the subsequent sections. <br /> PROPOSED SCOPE OF WORK <br /> The proposed scope of work has been subdivided into four general tasks, as outlined below. All <br /> work will be conducted under the direct supervision of a State of California Professional <br /> Geologist or Professional Engineer, and will be conducted in accordance with standards <br /> established by the Tri-Regional Board Staff Recommendations of Preliminary Investigation and <br /> Evaluation of Underground Tank Sites (RWQCB, April 2004). A California-licensed C-57 <br /> drilling contractor will perform all drilling and well construction activities. Stratus' Field <br /> Practices and Procedures that will be utilized during the investigation are included in <br /> Appendix A. <br /> Task 1: Pre-Field Activities <br /> Following receipt of SJCEHD's concurrence with the activities proposed in this work plan, the <br /> following activities will be completed: <br /> ■ Obtain well installation permits from SJCEHD. - <br /> ■ Retain and schedule a licensed C-57 drilling contactor. <br /> ■ Update the health and safety plan for the site. <br /> ■ Physically mark the drilling locations, and contract a private utility locating company and <br /> Underground Service Alert to locate underground utilities in the vicinity of the work site. <br /> ■ Notify the SJCEHD and the property owner of the scheduled field activities. <br /> K:\Parkinsons Hammer 1-5 Arco\Work Plans\Work Plan for Ozone Bench Scale Test.doc <br />