6.0 IMPLEMENTATION SCHEDULE <br /> A post-approval implementation schedule was prepared assuming Alternative 2 is approved <br /> for execution Site-specific groundwater monitoring was not considered because it is an <br /> established task Day 0 is assumed to be the regulatory approval date The proposed <br /> schedule is shown below <br /> Proposed Schedule <br /> Task Da <br /> Complete remedial mvestigation off-site 120 <br /> source search,work plan,and well mstalla- <br /> tion Identify compliance boundary <br /> Prepare and submit compliance contingency 180 <br /> plan <br /> Design,permit and construct SVE/bioventing 210 <br /> • system <br /> Commission and start-up SVE/bioventing 255 <br /> stem <br /> • 3201337B/1918REV 27 August 31, 1995 <br />