Laserfiche WebLink
i ' <br /> I <br /> Attachment 2-Figure 1 <br /> i Implementation Schedule <br /> Chevron Fuel Terminal 1001621 <br /> 22888 Kasson Road,Banta,California <br /> F=3 <br /> Task(Name Duration Start Finish 1 st Quarter 2nd Quarter- _ 3rd Quarter 4th Quarter _ 1 st Quarter 2nd Quarter 3rd Quart <br /> Jan Feb Mar A r Ma Jun Jul Aug 5e t3cE Nov Dec Jan Feb Mar _Apr Ma Jun Jul <br /> Remedial Action Plan 111 days) Mon 2111108 Tue 7!15108maw Preparat€on of Remedial Action Plan(RAP) 2 days! Mon 2111108; Tue 21'12108 <br /> Internal Review of RAP - - - -I 9 days) Wed 2113108, Mon 2125/08 <br /> 4 Client Review of RAP 10 days) Tue 2126108 Mon 3110!08 <br /> 5 d i ---- <br /> Submittal of RAP to Regional Water Quality Control Board(RWQCB) r 0 days, Thu 3113108 Thu 3113108 3113 <br /> 6 R RWQCB RAP Submittal Due Date 0 days, Mon 3117!08 Mon 3117108 3117 <br /> 7 RWQCB RE ew of RAP 31 days' Thu 3/13/081 Thu 4!24108 <br /> 8 _. .. -- _ <br /> ® RWQCB Comment Letter -- - - `-- - i p days Thu 4124I081 Thu 4124108 ® 4124 <br /> 9 ? Response to Comment 2 19 days Fri 4125108! Wed 5121108 <br /> 10 RWQCB Comment 2 Due Date 0 days Mon 5126108; Mon 5126108 ® 5126 <br /> - -- -- - ' <br /> 11 Response to RWQCB Comment 1 and 3 34 days! Fri 4125108! Wed 6!1110$ <br /> ___ _ _ _ <br /> 12 L RWQCB Comments 1 and 3 Due Date 0 days Mon 6116108, Mon 6116108 ® 6116 <br /> 13RWQCB Approval of RAP - 0 days Tue 7115108 Tue 7115108 ® 7115 <br /> -- - _ <br /> 14 Basis of Design 15 days' Mon 10/20/08 Fn 1117108 <br /> 15 Preparation of Basis of Design(BOD) 10 days; Mon 10120108! Fri 10131!08 <br /> 16 Internal Review and Acceptance of BOD - - � 5 days' Mon 1113108_ Fri 11/7/08 <br /> 17 Mechanical Drawings 43 days Wed 1213108! Mon 212109 <br /> 18 Equipment Selection 5 days. Wed 12!3108 Tue 1219108 <br /> -- _t.. - - -. -- -- - <br /> 19 Preparation of Mechanical Drawings 34 days Wed 12110108; Tue 1120109 <br /> 21 Drawings 1 final - - Tue 1!27109 Tue 1127109 <br /> 20 Review of Mechanical Drawings 5 days Wed 11211 <br /> Mechanical09 <br /> - -_ - <br /> O days- 1127 <br /> Tue 1127!09 <br /> 22 RWQCB Mechanical Drawings Submittal Due Date Oda s Mon 2!2109 Mon 212109 212 <br /> 3 Mon 212109 Mon 2116109 <br /> 23 ii days <br /> 24 Submittal of Mechanical Drawings to Contractor 0 da s;Contractor Selection <br /> Contractor -. Mon 212109! Mon 212109 212 <br /> 25 Contractor Review of Mechanical Drawings 5 days; Mon 2121091 Fri 216109 <br /> 26 Submittal 4646y by Contractor 1 day; Mon 2191091 Mon 219109 <br /> 27 Review of Bid by ARCADIS 5 days Tue 2!101091 Mon 2116109 <br /> 28 Acceptance of Bid by ARCADIS 0 days Mon 2/16/091 Mon 2116109 2116 <br /> �' 29 iPacific Gas and Electric Company(PG&E)Electrical Service 57 daysE Tue 2/17/091 Wed 516109 <br /> - ------ _. _. -- - - <br /> 30 PG&E Electrical Service Application Preparation - - 5 days Tue 2/17109 Mon 2123109 <br /> pp -- � 0 days Mon 21231091 Mon 2123109 <br /> __ m_ .. - - -- Wed- 52 days Tue?J24I09 Wed 516109 <br /> 31 PG&E Application Submittal � <br /> 32 PG&E Application Processing <br /> - _.. _... <br /> 33 PG&E Utility Drop 0 days! Wed 516/091 Wed 5/6109 516 <br /> - - -- - -—-- -- -- - _... _. -- - - <br /> 34 (Equipment Procurement 1 45 daysi Mon 3121091 Fri 511109 <br /> 35 s Equipment Procurement - 0 days' Mon 3/21091 Mon 312!09 312 <br /> System Construction/Shipping 45 days Mon 312109! Fri 511109 <br /> 37 System Delivery 0 days Fri 5!11091 - Fri 511109 511 <br /> 31 System Installation ACUVIt€es 21 days'; Mon 614109' Mon 511109 <br /> 39 Ed Kickoff Meeting 1 day'. Mon 514109 Mon 514109 <br /> 40 System Installation 15 days Tue 5151091 Mon 5125109 <br /> 41 Startup and Shakedown Activities 5 days Tue 5126!09,' Mon 611109 <br /> _..... <br /> 42 (System Operational - 0 days Mon 611/091 Mon 611109 611 <br /> I <br /> t <br /> I <br /> Project:RAP Implementation Schedule. Tasker Progress Summary V External Tasks Split <br /> Date:Mon 212109 Split Milestone 4 Project Summary °` External MileTask G' <br /> Page 1 <br /> i <br /> a <br />