Kennedy/Jenks Consultants <br /> Section 3: Work Plan Schedule <br /> The proposed schedule for the monitoring equipment installation will be as follows: <br /> 3 April 2006 —Submit Groundwater Investigation Work Plan <br /> 3 April 2006 — Initiate site reconnaissance and acquisition of offsite data <br /> • 1 May 2006 — Initiate offsite groundwater well data collection efforts <br /> 31 June 2006 — Complete CPT/HydropunchTM work <br /> • 31 August 2006 —Submit Addendum to Work Plan for Monitoring Well Installation (as <br /> needed) <br /> • 31 December 2006— Complete Monitoring Well Installation(s) (as needed) <br /> • 31 March 2007 —Submit Groundwater Characterization Report to CRWQCB <br /> Groundwater Investigation Work Plan Page 19 <br /> Barrel Ten Quarter Circle Winery, Escalon, California <br /> g:5s-groupladminGob1031030118.08_barreltenl0}reportslgw invest wrk phtextdoc <br />