K Kennedy Jenks <br /> Section 3: Groundwater Monitoring Well Installation Work <br /> Plan Schedule <br /> The work outlined in the Work Plan will be implemented by the following schedule: <br /> • February 2026 — Submit Groundwater Monitoring Well Installation Work Plan to the <br /> CRWQCB <br /> • Receive and respond to comments on Work Plan. <br /> • 45 Days Following Approval of Work Plan - Prepare Health and Safety Plan, select a <br /> licensed drilling contractor, and acquire drilling permits from San Joaquin County. <br /> • 120 Days Following Approval of Work Plan - Install, develop, and survey new wells <br /> (depending on contractor availability). <br /> • 60 Days Following Well Installation — Incorporate new wells into existing MRP and <br /> include data in the next Groundwater Monitoring Report. <br /> • 90 Days Following Well Installation — Submit Monitoring Well Installation Report <br /> (including reviewed laboratory reports and surveyor reports). <br /> Monitoring Well Installation Work Plan, The Wine Group, Franzia Winery, Ripon, California Page 8 <br /> \\kjc.local\kjc-root\kj-offce\sfo\projects\is-proj\2026\2665002.00_twg ripon gw mon well support\09-reports\mwisp\twg ripon mon well install wp_020426.docx <br />