`�Monitoring Well Installation Work Plan <br /> City of Stockton RWCF <br /> April 27,2005 <br /> Page 5 <br /> 7.0 PROJECT SCHEDULE <br /> Fieldwork will be initiated within approximately 30 days after approval of this work plan by the Regional <br /> Board and notification by the City of Stockton to proceed, subject to the availability of the drilling <br /> contractor. A report can be submitted to the Regional Board within six weeks of receipt by Condor of the <br /> laboratory analytical results. If you have any questions or need additional information, please call Jeff <br /> Willett at(209)234-0518. <br /> 8.0 LIMITATIONS <br /> Condor's responsibilities discussed in this work plan are limited to observing well installation, collecting <br /> and recording depth-to-water measurements and field parameters, collecting and shipping samples, <br /> compiling data provided by analytical laboratories, and interpreting field data. Condor is not responsible <br /> for the accuracy and completeness of information collected and developed by others. This work plan was <br /> prepared by Condor under the direct supervision of a Registered Engineer in the State of California. Any <br /> questions regarding the content of this document should be addressed to Mr. Jeff Willett at (209) 234- <br /> 0518. <br /> Case.� ktP-F 23 `f-o51�3 <br /> Respectfully submitted, <br /> CONDOR EARTH TECHNOLOGIES, INC. <br /> Micheline Doyle Kipf Jeff Willett,P.E. <br /> Staff Geologist Engineering Service Manager <br /> P:\3000_pg'\3596-City of Sro kton\3596Q Well IMta1la1ion\Repons\Work Plens\3596Q Work Plamdoc <br />