Laserfiche WebLink
pH Control System Modifications Compliance Schedule <br /> Dates : Action <br /> by 8/10/99 Compile list of engineering consulting firms qualified to design pH systems. <br /> by 8/15/99 Send request for proposal to all qualified engineering firms <br /> 09/01/99 Proposals due from engineering firms <br /> Review proposals with Dept. of Municipal Utilities <br /> 09/07/99 Choose engineering firm <br /> 9/7/99 thru 10/15/99 .Engineering firm to obseive factory operations and develop preliminary seasonal <br /> flow recommendations <br /> 10/15 thru 11/15 Engineering firm to observe factory operations and develop preliminary off season <br /> flow recommendations <br /> 12/01/99 Submit preliminary recommendations to Dept. of Municipal Utilities for approval. <br /> 12/10/99 Send request for proposal to mechanical contractors <br /> 12/20/99 Review bids from mechanical contractors <br /> 01/01/00 Begin construction of new pH control system <br /> 02/01/00 Complete construction & startup <br /> 02/15/00 Final Compliance <br />