Laserfiche WebLink
Emergency Remediation - 2480 Tracy Blvd., Tracy, CA. • Page 11 <br /> dispose of the contaminated water generated by this process are described in subsequent <br /> sections of this report. <br /> A total of approximately 350 cubic yards of contaminated soil, as measured in situ, was <br /> excavated by the remediation contractor to provide for construction of the basement <br /> foundation slab. This work was performed with a Komatsu PC-20OLC-5 excavator <br /> equipped with a 44 in. bucket. A Case 821 front loader with a 4 cu. yd. bucket was used <br /> to stockpile the excavated soil. <br /> Immediately after the basement excavation was complete, the remediation contractor <br /> placed and compacted rock and sand sub-base materials to receive the basement slab <br /> concrete. As soon as that work was complete, the concrete sub-contractor graded the base <br /> materials, installed the reinforcing steel and poured the slab without delay. The basement <br /> structure was then completed and the waterproofing contractor bentonite-fabric <br /> waterproofing material was applied to the exterior of the walls. <br /> When the space between the basement walls and the perimeter of the excavation was <br /> backfilled, the waterproofing contractor extended the previously-installed dewatering <br /> drains upward to conform with the new elevation of the basement slab. This will allow any <br /> vadoze zone water that accumulates behind the basement walls to drain away. <br /> Later in the remediation project, contaminated soil was excavated to install a 10,000 <br /> gallon wash-water recycling tank. This operation generated approximately 60 cu. yds. of <br /> contaminated soil. The remediation contractor performed the excavation work, placed <br /> bedding materials in the bottom of the tank pit, set the tank into position, and placed the <br /> granular backfill around it. Because the bottom of the tank pit was at a depth of <br /> approximately 12 ft. beneath the ground surface, the tank was submerged below the water <br /> table to a depth of some 4.5 ft when set in its final position. <br /> To effect the tank installation without pumping contaminated water, the deepest portion of <br /> the tank pit was opened by extracting below the water table. Rock and pea gravel was <br /> placed in uniform layers in the bottom of the flooded pit and the tank settled onto it by <br /> filling the tank with water until it slowly sank. Ropes were used to maintain the tank in the <br /> correct position and orientation as was submerged Approximately 8,000 gallons of clean <br /> water that had been treated and tested after it had been pumped from the basement <br /> dewatering system were used for this purpose. The procedures used to treat and test that <br /> water are described later in this report. <br /> Excavation of contaminated soil by the remediation contractor was strictly limited to the <br /> minimum required for construction of the car-wash and automobile-lubrication facility. <br /> However, it was found that the spoil heaps generated by the first phase of excavation for <br /> the basement, which was underway when gasoline-contaminated soil was first identified, <br /> contained comingled clean and contaminated soil which it was not practical to segregate. <br /> Thus, all of the soil excavated from the basement pit was handled as though it were <br />