• COST TABLE it
<br /> REMEDIATION EQUIPMENT AND SYSTEM INSTALLATION COSTS
<br /> Former Canteen Facility
<br /> 1500 Shaw Road
<br /> Stockton, California
<br /> Capital Equipment Qty Units Unit Cost Item Costs
<br /> Air Sparging Compressor, 3-HP, 240V, 3� Power 1 ea $ 3,250 $ 3,250
<br /> Control System 1 ea 2,050 2,050
<br /> In-Line Flow Meters (Rotometers) 7 ea 125 875
<br /> Skid-Mounting of Sparging Equipment 1 LS 2,100 2,100
<br /> Soil Vapor Extraction Blower, 10-HP, 240V, 3� Power 1 ea 6,200 6,200
<br /> Control System 1 ea 2,050 2,050
<br /> In-Line Flow Meters (Venturi) 5 ea 540 2,700
<br /> Skid-Mounting of SVE Equipment 1 LS 2,100 2,100
<br /> Internal Combustion Engine Unit Costs (See O&M Rental Costs) 0 months 8,408 ---
<br /> ICE Unit-Mobilization 1 Start-up 1 Emissions Permitting 1 LS 2,700 2,700
<br /> Telemetry System (Standard Phone Line Type) 1 LS 3,050 3,050
<br /> Shipping for the Skid Equipment 1 LS 2,700 2,700
<br /> Equipment Mark-Up-Cost + 10% 1 ILS 2,9781 2,978
<br /> Subtotal $ 32,753
<br /> Installation Costs Qty, Units Unit Cost Item Costs
<br /> Mob 1 Demob I Safety Plan 1 LS $ 3,200 $ 3,200
<br /> Obtain City Permit(s), OSHA Excavation Permit 1 LS 5,500 5,500
<br /> Line Locators 1 LS 800 800
<br /> Sawcuttmg, Breaking, and Trenching-Asphalt Section (2 S wide) 360 lin ft 1695 6,102
<br /> Trench Plumbing-Asphalt Section (Materials & Labor) 360 lin ft 3500 12,600
<br /> Bedding Sand 80 tons 2200 1,760
<br /> Stabilized Backfill 40 tons 2025 810
<br /> Backfill & Compaction 360 lin ft 750 2,700
<br /> Access Manways for AS/SVE Wells (Materials & Labor) 18 ea 150 2,700
<br /> Well Head Plumbing (ASISVE Wells)-Tubes and Hoses 18 ea 120 2,160
<br /> Trench Resurfacing (Asphalt) 700 sq ft 450 3,150
<br /> Traffic Control Safety Barricades for Trenches 1 LS 500 500
<br /> Concrete Equipment Slab 224 sq ft 1750 3,920
<br /> Remediation Compound Enclosure (6-foot Cedar-Slat Fencing) 1 LS 4,200 4,200
<br /> Install AS Control Manifold (13 Wells) 1 LS 1,750 1,750
<br /> Install SVE Control Manifold (5 Wells) 1 LS 1,750 1,750
<br /> Electrical Panel 1 Pole & Wiring to Control Panels Budd 3� Bank 1 ea 6,250 6,250
<br /> Installation Mark-Up-Cost + 10% 1 LS 5,985 5,985
<br /> Subtotal $ 65,83711