July 27, 2011 <br /> AEI Project No. 299162 <br /> Page 5 of 5 <br /> VI Estimated Schedule <br /> Completion of this work is contingent upon approval of this work plan and receipt of approved <br /> drilling permits. It is anticipated that the approved drilling permits will be received <br /> approximately one week following their submittal and that field activities will commence one to <br /> two weeks thereafter, pending subcontractor availability. Laboratory analytical results will be <br /> obtained within approximately one week following the sample collection. A final report will be <br /> prepared and submitted to the client and the EHD within approximately one week following the <br /> receipt of analytical data. <br /> AEI requests your comments and approval to proceed with this project. Please contact the <br /> undersigned at (925) 746-6000 extension 141 if you have any questions or need any additional <br /> information. <br /> Sincerely, <br /> AEI onsu/tants <br /> Harmony TomSun <br /> Project Geologist <br /> Figures <br /> Figure 1 Site Location Map <br /> Figure 2 Site Plan <br /> Attachments <br /> Attachment A Phase I ESA <br /> Attachment B Health & Safety, Injury & Illness Prevention Plan <br />