low <br /> SECTION 1 <br /> PAGE OF <br /> 2. PLANNED ACTIVITIES FOR THE FOLLOWING QUARTER ( 1 Oct 89 thru 30 Dec 89) <br /> 1. Start construction of North Balloon Groundwater Treatment System. <br /> 2. Complete the installation of Automated Groundwater Level Monitoring <br /> System. Performing the final testing (Oct 89) . <br /> 3. Removal of un-needed Underground Storage Tanks (USTs) and replacement r <br /> of needed UST's. Contract Performance Period Oct 89 thru Apr 90. <br /> f <br /> r <br /> 4. Construction of Hazardous Waste Staging Facility. <br /> 5. Set up a RI/FS Technical Committee meeting to discuss SHAD' s Work <br /> Plan. Tentatively this meeting is set up for 19 October 1989. Attendees <br /> will include representatives from all parties to the agreement and contractor <br /> performing the RI/FS investigatory work. <br /> 6. VOC Air Sampling will continue this quarter by USATHAMA Contractor <br /> (ESE) . <br /> 7. Arsenic Study contract will be established by USATHAMA. <br /> 8. Arsenic Removal Pilot System will be delivered to SHAD during this <br /> quarter for installation during the first quarter of calendar year 1990. <br /> 9. Prepare and submit South Balloon Groundwater Treatment System Monthly <br /> NPDES report on or by the 15th of the month. <br /> 10. Storm Drainage System TV Survey will commence this quarter <br /> (tentative) . <br /> 11. Repairs of Sanitary Sewerlines will continue. Scheduled completion <br /> is approximately 15 November 1989. <br /> ,�,' h i <br />