EXHIBIT E <br /> SCHEDULE <br /> CABRAL — MCADAMS PROPERTY <br /> TASK SCHEDULE* <br /> Draft PEA work plan (including health and Within 60-days of VCA approval <br /> safety, QA/QC plan, and community profile <br /> DTSC review/comment on the draft work Within 15-days of submittal of the draft work <br /> plans plans <br /> Revised work plans Within 10-days of DTSC comments on the <br /> draft work plans <br /> Finalize work plans Within 5-days of receipt of revised work <br /> plans <br /> Field work Within 30-days of receipt of finalized work <br /> plan <br /> Draft PEA report Within 60-days of completion of field work <br /> DTSC review/comment on PEA report Within 30-days of receipt of draft PEA report <br /> Finalize PEA report Within 15-days of DTSC comments on the <br /> draft PEA report <br /> DTSC PEA report approval Within 15-days of receipt of finalized PEA <br /> report <br /> *All days are calendar days unless specified otherwise. <br />