DAILY FIELD REPORT Page 1 of 1 <br />Project Name: Foothill Sanitary Landfill - Area 2A Report Number: 078 <br />Project Number: 14-101-01 Date: Thursday 08/27/15 <br />Owner: Dept. of Public Works, San Joaquin County CQA Monitors: R. Nogales <br />Contractor: R J Gordon Construction, Inc. M. Hu and <br />Weather: Clear - Hot Wind: 0-10 mph. <br />Temperature: ApErox. range 68- 104 F Other: <br />The contractor worked from 5:00 am to 4:30 pm. <br />Operations Layer Processing: Contractor continued screening of operations stockpile today at 6:00 am. (1) Hyundai 480 <br />excavator, (1) CAT D6 dozer (1) 950 M Loader was used to perform screening operations. Hyundai 480 excavator was used to <br />load soil from the Western end of Stockpile 2 into the Power Screen screening plant. Screened product was stockpiled in a <br />cone using a belt stacker to keep the screened soil separate from unprocessed soil. (1) 950 M Loader was used relocate +1" <br />from under the belt into separate stockpile. (1) Sample collected from today's stacker belt stockpile. Full gradation was <br />performed in field lab. Lab results indicated 100 % Passing 1" Screen. Screening operation ended at 3:30 pm. <br />Operations Layer Placement: No activity observed today. (6) Operations Layer Samples from placed material were collected <br />to send to Soils Laboratory for analysis. <br />Gravel Drainage Material Placement: 19-20 various types of end -dumps were used to import Gravel Drainage Material <br />(GDM) from the Cemex Rock Plant until 4:30 pm. Observed trucks operating on at least 3 ft of GDM overlying the <br />Geomembrane. (1) CAT D6 LGP dozer equipped with GPS spread GDM in the center of cell floor pushing West this morning <br />beginning at 5:00 am. (1) Laborer controlled wrinkles. GDM placement discontinued at approximately 11:00 pm due to <br />moderate to heavy wrinkles observed in HDPE Liner. GDM import continued, with material stockpiled onto previously <br />deployed GDM. Stockpiling was supported by the CAT D6 LGP Dozer and CAT D4 Dozer. AES QA personnel monitored the <br />placement and verified the depths of the placed LCRS gravel by using a dulled probe. (1) GDM sample was collected at 9:30 <br />am. Field gradation indicated the GDM met the specifications. <br />Geotextile: No activity observed today <br />Geocomposite: Geocomposite deployed on balance of east slope and portions of North slope. Observed nylon ties secured at <br />3 foot intervals along length and 6 -inch intervals along width. Geotextile seams were sewn using hand sewing machine. <br />Installation resulted in horizontal seams on the slope. Horizontal seams are used on alternate runs down the slope, with <br />single panels extending to the toe of slope on both sides of any horizontal seam. <br />Leachate Collection Pipe: Contractor installed portions of Northern and Middle Leachate Collection Pipe. Approximately <br />100 If of 6" perforated HDPE pipe was placed today. (1) John Deere 410 Backhoe and (1) Cat 950 M Loader operating over <br />completed operations layer soil was used to place coarse gravel over 6" Perforated HDPE Pipe. Coarse gravel and 6" HDPE <br />pipe was wrapped in 8 oz/sy Geotextile. Gravel was measured to be a minimum 1 ft deep and a minimum 4 ft wide. Geotextile <br />was measured to have a 2 ft minimum overlap. <br />24" HDPE Riser Pipe: No activity observed today. <br />Equipment Onsite: (1) CAT D6T LGP dozer, (2) water trucks, (1) Hitachi 300 excavator, (1) CAT TH160B folk lift, (1) John <br />Deere 410 Backhoe. (1) CAT 623 paddlewheel scraper. (1) Power Screen, (1) Belt Stacker, (1) Hyundai 480LC excavator, (1) <br />CAT D6T dozer, (2) Cat 745 Dump Truck, (1) Cat 950 M Loader (1) CAT D4 Dozer <br />Problems/Resolutions. <br />Visitors: <br />Reviewed By: M. Raub <br />y <br />