07/22/99 Construction Field Report Job No. 986011.0: <br /> DFR No. 55 VECTOR ENGINEERING, INC. Page No. 1 <br /> Project Name: Client Or Owner: Daily Field Report Sequence No.: <br /> Forward Landfill Allied Waste 55 <br /> Location Of Work: Owner's Or Client's Representative: Date: Day Of Week: <br /> Mant2S CA Butch SteffiniJr. 7-22-99 Thursda <br /> General Contractor: Liner Contractor: Proj. Engineer: Reviewed By: <br /> Guinn Construction GSE Scott Purdy <br /> General Forman Liner Contractor Superintendent Or Foreman: <br /> Duane Meadows William Gea <br /> Source And Description Of Fill Material: Weather: CQA TechnicianlTechnidw. <br /> Clear Warm FRANK DELL-ERA <br /> Equipment used: <br /> Guinn: 140G Grader,3-633/1-623 Paddle Wheels,D4H Cat Dozer,D5H Cat Dozer,320L Cat Excavator,966D Cat loader,Water <br /> Ttuc CS 563C Cat Smooth Drum Roller.GSE:544E John Deere Loader Gradall. <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> Guinn Crew: 7 total GSE Crew: 12 total <br /> Guinn continues to place geotextile and operation layer material over the approved GDM. Guinn placed a 3' <br /> extension onto the 6"LCRS pipe running from the west towards the east so the pipe would lay in the bottom <br /> of the V ditch on the eastern edge of the cell. Guinn reconnected the 6"LCRS pipe tying into cell WMU D- <br /> 98 in the eastern V channel. Guinn excavated and backfilled the anchor trench across the southern roadway. <br /> Guinn excavated the anchor trench on the southern bench in the southwest comer of cell WMU D-99. <br /> GSE completed deployment of the geocomposite from the southern slope of cell WMU D-99 down to the <br /> cell floor. A total of 11 panels were placed with approximately 7.592.5ft2. GSE cleaned up the site of <br /> garbage. GSE pulled back and placed the liner in anchor trenches as Guinn excavated thein. GSE left the site <br /> today. <br /> Vector Engineering,Inc.CQA observed placement,over lap,tying and sewing of the geocomposite. CQA <br /> observed placement of operations material. Checked depth and verified thickness on portions of the GDM. <br /> File Name: Forward Landfill Prepared by: Frank Dell-Era Reviewed by: US <br />