17ECTOR <br /> ENGINEERING IWC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Daily Field Report Sequence Number: <br /> Forward Landfill 021605.03 88 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Manteca, Ca Butch Stefan Forward, Inc. January 5,2004 Monday <br /> General Contrdcstor Liner Contractor. Project Engineer: <br /> Sukut Construction GSE San Beta Lewis <br /> General Foreman: Liner Superintendent: Others: <br /> King Bailey Ayre Khounmouan <br /> Source and Description of Fill Material: Weather: CQA Technician. <br /> Native,stockpiled,light brown silty Clay Cold,clear and breezy Ken Davila <br /> Equipment on site: <br /> 1-D6 LGP dozer 1-backhoe, 1-sera er <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> On site today for documentation and observations at the location listed above. I met with the Sukut <br /> foreman in the early morning to discuss this week's plan of attack. He stated that they would remove the <br /> mud from the area,begin hauling ops layer tomorrow and on Wednesday begin hauling granular drainage <br /> material. <br /> They began removing the saturated material from the top of the clay stockpile with the dozer in <br /> preparation for tomorrow's operations layer hauling. The sump pump continued pumping rainwater from <br /> the sump area throughout the day. Laborers rolled out the geotextile which had been wind blown from the <br /> south central FLT-03 cell floor. <br /> Rainwater had run off the northeast slope just east of the cell and had run under the liner at the end of the <br /> grouted anchor trench. Water had collected under the liner at the point where the gravel placement had <br /> stopped, approximately 100 feet south of the 2:1 toe of slope. After discussing this with the Vector project . <br /> manager,Montie C.,at approximately 11:30am a hole was cut in the liner to release the water and let it flow <br /> in the east"V"ditch on top of the liner. The water continued to flow for approximately four hours. At a <br /> later date,the secondary clay liner will be inspected for water damage. <br /> In the late afternoon,Butch S. (Forward)stated that there is a meeting scheduled for tomorrow at 11:00 <br /> am. <br /> Prepared By: Reviewed By: <br /> 4/23/03,Rev. 0 1 of 1 <br /> ra <br />