Final Construction Quality Assurance Report —WMU FU -13 <br />Forward Landfill <br />passing the #200 sieve. <br />Hydraulic conductivity testing of the granular drainage material indicated an average flow rate <br />greater than 3-5 cm/sec, which exceeds the requirement of 0.1 cm/sec. Hydraulic conductivity <br />testing of the coarse gravel drainage material indicated an average flow rate greater than 10.0 <br />cm/sec, which exceeds the requirement of 1 cm/sec. The laboratory test results of the granular <br />drainage material and coarse gravel testing are included in Appendix F and Appendix G, <br />respectively. <br />4.6 PROTECTIVE OPERATIONS LAYER <br />Upon completion and approval of the LCRS granular drainage layer and deployment of 8 oz/yd2 <br />filter geotextile (discussed in detail in Section 5), a one -foot thick lift of protective operations <br />layer soils was placed on the floor, and also pushed 10' up the 2:1 slope of WMU FU -13. <br />• <br />The protective operations layer soils were placed by scrapers by spreading the on-site moisture <br />conditioned soil in a minimum 12 -inch continuous loose lift over the filter geotextile and LCRS <br />gravel drainage (material using a GPS controlled D6 CAT dozer). GLA's CQA Monitor observed <br />the Contractor's activities during placement of the operations layer soils to minimize the • <br />potential for damage to the underlying geosynthetics. <br />4.7 ANCHOR TRENCHES AND TERMINATION BERMS <br />Prior to commencement of geomembrane deployment, GLA's CQA Monitor observed that the <br />anchor trenches were constructed according to the details in the Plans and Specifications, and <br />were free of loose soil or deleterious material. After completion of geosynthetics deployment, <br />GLA's CQA Monitor observed and documented that the backfill for the anchor trenches was <br />placed and compacted in accordance with the Specifications, and that no damage occurred to <br />the geosynthetics material during backfill operations. GLA's CQA Monitor performed two (2) <br />tests (CL82-83) in the clay plug anchor trench backfill for the geosynthetics deployed on the 4:1 <br />slope. Documentation of the anchor trench backfill compaction test is included with the tests <br />performed on the low permeable clay liner soils in Appendix D. <br />Termination berms were constructed along the south and east sides of FU -13 to prevent <br />surface water run-on into the module. Construction of the temporary termination berms was <br />observed by GLA's CQA Monitor to ensure that the Contractor was placing and compacting <br />moisture conditioned soils in such a manner as to produce a firm and unyielding condition. • <br />These termination berms were constructed using on-site soils. <br />16 Geo -Logic <br />ASSOCIATES <br />