Laserfiche WebLink
C <br />Preliminary Closure Cost Estimate <br />(continued) <br />LFG MONITORING AND CONTROL SYSTEMS <br />8.0 Assume three replacement LFG migration monitoring wells will be installed. Each will consist of 3 probes. <br />Existing LFG multi probe depth 70 feet, at $150/ft (UCB unit cost) = $10,500 per replacement. <br />9.1 Disabling and rebuilding LFG emission control system; Repair of above -ground field components at 30% of original cost. <br />(See Page D-5). Cost estimates provided in sheet D-5 remain valid. <br />9.2 A portion of the above -ground LFG emission control system components will be replaced during closure; Replacement at <br />15% of original cost. (See Page D-5). Cost estimates provided in sheet D-5 remain valid. <br />GROUNDWATER MONITORING SYSTEM <br />10.0 Assume two new groundwater monitoring wells will be installed. In addition, this cost should cover repairs to all of the <br />wells at closure. Well replacement at $75/ft UCB unit cost, for 140 foot depth = $10,500. <br />DRAINAGE SYSTEM <br />11.0 The in place storm drain piping, assessed to consist of about 5,000 linear feet of 18 -inch to 42 -inch diameter piping with <br />bench inlets, will be protected in place and/or salvaged and relayed during final cover placement, estimated unit cost of <br />$25 per liner foot. Unit UCB to install 18 -inch CMP is $70/LF; 36 -inch CMP is $103/LF, both for limited quantities. The <br />allowance of $25/LF to protect in place, and allow for some salvage and relay remains valid. <br />SECURITY INSTALLATION <br />12.0 Fencing will be placed around the entire site as it is developed. The cost for closure includes approximately 2,500 feet of <br />fencing replacement with a locked access gate. Use $35/LF; UCB unit cost is $25/1-F. <br />STRUCTURAL REMOVAL <br />13.0 Structures to be removed include the scalehouse, office and maintenance buildings, 43,210 SF (based on 1990 PCPC <br />Plan). Demolition cost assumes buildings on 4" concrete slab (R S Means, 2004; adjusted for inflation). Costing at <br />$4.50/SF remains valid. <br />DECOMMISSION OF ENVIRONMENTAL MONITORING I CONTROL SYSTEMS <br />14.0 Decommissioning of the internal soil gas wells will be included in module development costs. <br />SURVEY MONUMENTS <br />15.0 Install a maximum of four survey monuments on final cover; only two required by regulations, costing adequate. <br />PROFESSIONAL SERVICES <br />16.0 Prepare FC and PCP for agency approval. Price based on Shaw experience. <br />17.0 Prepare closure construction drawings, specifications, and contract documents. Price based on Shaw experience. <br />18.0 Assume aerial topographical survey with 2 -foot intervals. Cost based on 2007 topographic survey for the site at $18,000. <br />19.0 Assume 5% of the final cover installation. <br />CONTINGENCY <br />Title 27 Section 21820 requires that costs be increased by 20% to account for cost over -runs. <br />PCMP for NCRCSL D-4 <br />0.1San Joaquin CountylNCRCZ1180401PCPMPIFinal ReporflPCPMP_Rev_Jan_2010.Doc <br />Department of Public Works/Solid Waste <br />County of San Joaquin - January 7, 2010 <br />