On April 23, 2012, the County submitted a revised and preliminary Final Cover Expansion <br /> Design, incorporating a low density polyethylene membrane. This letter included a preliminary <br /> schedule showing completion in December 2012. <br /> On May 31, 2012,the County submitted a Final Cover Expansion Design incorporating review <br /> comments received by RWQCB staff. Reconsideration of the schedule by Shaw Environmental <br /> indicated project completion in March 2013. <br /> On June 6, 2012,the County submitted a revised schedule showing bidding in late 2012 with <br /> construction starting in the spring of 2013. A letter dated July 13, 2012 apparently tentatively <br /> accepted that revised schedule. <br /> Corral Hollow Sanitary Landfill 6 Department of Public Works/Solid Waste <br /> 2nd Quarter 2012 Groundwater Monitoring County of San Joaquin—July 30,2012 <br />