(2/94) <br /> Sec. 10-1, Construction Details <br /> Std. Spec. Sec. 19 <br /> Special <br /> Page 2 of 4 <br /> The clay barrier layer (barrier) shall be constructed as follows: <br /> A on-site selected soil shall be placed on the finished <br /> foundation layer. <br /> B. on-site selected soil shall be spread over the finished <br /> foundation layer in a single loose layer of <br /> approximately 13 inches. (The 13-inch thickness may be <br /> adjusted to allow for a final compacted barrier layer <br /> of 12 .5 inches minimum. ) <br /> C The 20 percent imported lone clay shall be spread <br /> evenly over the uncompacted ,13-inch loose lift. This <br /> should give an uricompacted clay depth of approximately <br /> 3 inches. <br /> As a guide for determining necessary quantities of lone <br /> clay, a 500-foot x 500-foot square area will require <br /> approximately 3,500 Tons. <br /> The Contractor shall not begin premixing until the <br /> Engineer has approved the spreading of lone clay. <br /> D. A motorized pug mill mixer capable of injecting water <br /> into the mixing chamber at a controlled rate (CAT RR- <br /> 250 Soil Stabilizer, or approved equal) shall be used <br /> to initially break the 20 percent imported lone clay <br /> clods and to mix the soil. The mixer shall have a <br /> minimum mixing depth of 16 inches and shall be equipped <br /> with "bullet" cutting teeth. The mixing chamber shall <br /> be set to a depth of approximately 4 inches and the <br /> mixing bar shall rotate at a minimum speed of 160 rpm. <br /> A minimum of two passes (premixing) shall be made with <br /> the mixer without adding any moisture to break the 20 <br /> percent imported lone clay clods. Premixing shall <br /> continue until a maximum of 10 percent is retained on a <br /> 3/4-inch sieve. Cobbles and cemented particles larger <br /> than 1 1/2 inches, and foreign material, shall be <br /> removed by the Contractor. <br />