Laserfiche WebLink
7 SCHEDULE <br /> May 23, 2008-Submit Plan <br /> June 6, 2008-Agency Response <br /> June 23,2008-Install PGP-1 A and PGP-2A <br /> June 26,2008-Monitor PGP-1 A and PGP-2A <br /> July 3,2008-Verify Results of Initial Monitoring of PGP-1 A and PGP-2A (if necessary) <br /> July 28, 2008- Install Initial Vent Wells Adjacent to PGP Locations Exhibiting Elevated Methane (if <br /> necessary) <br /> July 30, 2008-Conduct Radius of Influence Testing (if necessary) <br /> August 2008-Complete Detailed Engineering (if necessary) <br /> September 2008 - Modify Vent Well Network in Accordance with Detailed Engineering (if <br /> necessary) <br /> 15 "'MILLER HAW OKS <br /> P:\707 Cove Contractors\Feasibility Study and Corrective Action Plan\Corrective Action Plan_Final.doc <br />