E21 May 2003 <br /> AGE-NC Project No 95-0130 <br /> Page 7 of 16 <br />' should be adequate to address interim remediation efforts in the `core' area of the dissolved <br /> petroleum hydrocarbon plume, proposed ground water extraction well locations and results of the <br /> capture zone analysis are illustrated in Figure 3 AGE proposes installation of ground water <br /> extraction wells in the following locations <br /> • A six-inch diameter ground water extraction well (EW-1) screened between 30 and 55 feet <br />' bsg(Hydrologic Unit No 1)and located approximately 5 to 15 feet north of monitoring well <br /> MW-6, and <br />' • A six-inch diameter ground water extraction well(EW-2) screened between 30 and 55 feet <br /> bsg{Hydrologic Unit No ])and located approximately 10 to 20 feet northeast of well VW-2 <br /> IFollowing installation of ground water extraction wells EW-1 and EW-2,AGE will install dedicated, <br /> four-inch diameter Grundfos submersible pumps (model 5E5) inside each extraction well The <br /> pumps will be designed to operate continuously at low flow rates ranging between five and ten <br /> gallons per minute (GPM) Additional information for the proposed submersible pumps are in <br /> Appendix A <br /> I� <br /> 3 3 INSTALLATION OF INTERIM REMEDIATION SYSTEM PIPING NETWORK <br /> IA remediation system piping network will be installed underground in a 1%rfoot wide by a 1'/z-foot <br /> deep trench, the proposed trenching location is depicted in Figure 5, a cross sectional view of the <br />' trench is depicted in Figure 6 In the trench, two-inch diameter, schedule 80 PVC piping will be <br /> 1) manifolded from the well-heads at VW-1, VW-2, VW-3 and routed to the proposed vapor <br /> extraction unit,and 2)manifolded from the well-heads at EW-1 and EW-2 and routed to the ground <br /> I water treatment system Following piping placement, the trench will be backfilled with imported <br /> road-base sand, compacted and resurfaced with concrete <br />' Installation of a 20-foot wide by 40-foot Iong, chain-link, gated enclosure will be located in a <br /> southwest section of the site to secure the vapor extraction unit and the ground water treatment <br /> system The proposed remediation system fencing enclosure is illustrated in Figure 5 <br /> 34 PROPOSED INTERIM SOIL REMEDIATION SYSTEM <br />' TheY <br /> ro osed interim remediation SVE system will consist of a vacuum blower(Solleco Ecat 250) <br /> p P <br /> and a catalytic converter The two-inch diameter piping installed underground from the well-head <br />' at wells VW-1, VW-2 and VW-3 will be connected to the inlet of the vacuum blower, the outlet <br /> • from the vacuum blower will be routed through a catalytic converter Induced vacuum will measured <br />' Advanced GeoEnvironmental,Inc <br /> I <br />