IMPLEMENTATION SCHEDULE <br /> The proposed additional site characterization will be completed and a report submitted within <br /> 90 days after receipt of written approval of the proposed work plan from the appropriate <br /> regulatory agencies. The estimated schedule for completion of the proposed tasks is as follows: <br /> Dnyq Aftar Wnrk <br /> Tack f Arty Pla�z rnval <br /> -Acquire permits 15 <br /> -Drill soil borings and collect soil and groundwater samples 35 <br /> -Analyze soil and groundwater samples 60 <br /> -Evaluate data 75 <br /> -Prepare report 90 <br /> L <br /> 4 <br />