Laserfiche WebLink
CPSA GWET and SVE Systems Decommissioning Activities Work Plan Page 3 <br /> Lodi Central Plume Source Area,Lodi,California <br /> March 4,2021 <br /> ■ A Notification of Soil Excavation from the Water Board to be distributed to <br /> the residential and commercial property residents and owners prior to <br /> commencement of soil excavation activities; and, <br /> ■ Site access agreements with nearby private property owners, if needed. <br /> • Underground Utility Survey <br /> Prior to initiating excavation or subsurface investigation work, the Contractor will <br /> mark all excavation areas in white paint and contact Underground Service Alert <br /> (USA)at least 72-hours prior to the start of fieldwork to notify local utilities of the <br /> planned work. Additionally, a private utility locator will search for other on-Site <br /> subsurface utilities and/or obstructions that may or may not be marked by USA. <br /> B. GWET and SVE System Decommissioning — The above-ground components of the <br /> GWET and SVE systems, including granular activated (GAC) carbon vessels / tanks, <br /> filters, and aboveground piping and valves will be dismantled and removed for disposal or <br /> recycling, and spent GAC will be profiled for proper disposal to an appropriate off-site <br /> disposal facility. The piping for the GWET and SVE systems, as well as any utility lines <br /> associated with the CPSA remedial systems (Figure 3), will either be removed, and/or <br /> grouted, capped, and abandoned in place,as per City of Lodi requirements. Additionally, <br /> the Treatment System compound will be dismantled and all its relevant components <br /> including fencing,concrete pad,control and instrumentation panels,manifolds, and sumps <br /> will be dismantled and removed for recycling or disposal to an appropriate off-site disposal <br /> facility. <br /> C. Well Abandonment—Prior to abandonment of the groundwater extraction and soil vapor <br /> extraction and monitoring wells, the driller will obtain all the necessary permits for well <br /> abandonment from the San Joaquin Department of Environmental Health (SJDEH). <br /> Appropriate methodologies will be adopted for abandoning the SVE and vapor monitoring <br /> (VMW)wells and the groundwater extraction wells. <br /> a. All SVE and VMW wells will be properly abandoned by over-drilling using an <br /> oversized hollow stem augur drills based on the diameter of the wells. For the 2- <br /> inch diameter SVE and vapor monitoring wells an 8" outer diameter(OD)auger <br /> fitted with a 9" bit will be used, while for the 4-inch diameter SVE and vapor <br /> monitoring wells, a 10" OD auger fitted with a 11" bit will be used to over drill the <br /> well casing.The over-drilled borehole will be grout sealed using the tremie system <br /> to the target depth following removal of the well casing. <br /> b. Groundwater extraction wells EW-04, EW-05, and EW-06 will be properly <br /> abandoned using the appropriate method approved by SJDEH, which will include <br /> perforation of the steel casing and pressure grouting. <br /> 175 N EL MONTE AVENUE,LOS ALTOS,CA 94022 TEL:415-424-3009 <br />