Fire No S-1739-1 <br /> H. KLEINFELDER & ASSOCIATES October 19 , 1982 <br /> TABLE I <br /> SUMMARY OF FIELD DENSITY TEST RESULTS <br /> is Dry Laboratory Specified <br /> Test Moisture Density Compaction Relative Relative <br /> No. Date Test Location *FSG Dry Wt. P.C.F. Curve No. Compaction Compaction <br /> COMPACTED FYIBANKMENT <br /> 14 10-7 425' From S End -35.0' 17.9 104.8 3 91 90% <br /> 15 10-7 50' From S End -35.0' 21.0 96.4 2 91 90% <br /> 16 10-7 150' From S End -29.0' 17.0 107.8 3 94 90% <br /> 17 10-7 300' From S End -23.0' 17.7 106.0 3 92 90% <br /> 18 10-7 S End -18.01 16.5 106.1 3 92 90% <br /> 19 10-8 S End -12.01 16.2 109.0 3 95 90% <br /> 20 10-8 175' From S End -23.01 17.3 108.5 3 94 90% <br /> 21 10-8 Center -33.01 16.0 108.7 3 95 90'% <br /> 22 10-8 2501 From N End -33.0' 18.2 10510 3 91 90% <br /> 23 10-8 S End of E -10.01 18.1 103.6 3 90 90% <br /> Embankment <br /> 24 10-8 Middle of E -22.0' 16.4 106.7 3 93 90% <br /> Embankment <br /> 25 10-11 501 From S End -6.0' 17.0 108.3 3 94 90% <br /> 26 10-11 1901 From S End -12.0' 16.8 107.3 3 93 90% <br /> 27 10-11 275' From S End -18.0' 17.9 104.8 3 91 90% <br /> 28 10-12 Middle of E -10.01 16.3 103.6 3 90 90% <br /> Embankment <br /> 29 10-13 2751 From N End -12.01 17.3 104.2 3 91 90% <br /> 30 10-13 1751 From N End -20.01 17.4 105.6 3 92 90% <br /> 31 10-13 751 From N End -26.0' 17.4 103.5 3 90 90% <br /> 32 10-14 100' From N End FSG 17.4 107.4 3 93 90% <br /> 33 10-14 Center of N End - 0.5' 16.9 106.7 3 93 90% <br /> 34 . 10-14 201 From W End -7.01 17.6 107.7 3 94 90% <br /> *DENOTES <br /> --FINISHED Accepted engineering and testing procedures were used for these tests. The above data is presented for in- <br /> SUBGRADE formation purposes only. In the absence of continuous observations of our personnel at the site, we can not <br /> express an opinion as to the adequacy of site preparation or overall fill compacfion. We do not undertake the <br /> guarantee of construction, nor do we relieve the contractor of his primary responsibility to produce a com- <br /> pleted project conforming to the project plans and specifications. <br /> IHK&A Form R-20 <br />