Laserfiche WebLink
Drilling Work Plan <br />Project No.: 1086 <br />March 16, 2022 <br />Two Borings will be drilled on the North Side of E. Lafayette Street Right -of -Way: <br />• Five borings at location CPT -15 will be installed to close data gaps in the 1,2 -DCA <br />plume immediately north of the Site. <br />• Five borings at location CPT -16 will be installed to close data gaps in the 1,2 -DCA <br />plume immediately north of the Site. <br />Three Borings will be drilled within the Cal Trans Right -of -Way: <br />• Five borings at location CPT -12 will be installed approximately 450 feet northeast of <br />CPT -8 and approximately 800 feet down -gradient of the furthest up -gradient end of <br />the former UST pit (source) and beyond the expected edge of the groundwater plume. <br />• Five borings at location CPT -13 will be installed approximately 650 feet northeast of <br />CPT -9 and approximately 850 feet down -gradient of the furthest up -gradient end of <br />the former UST pit (source). CPT -13 would be the furthest down -gradient boring <br />installed to date. <br />• Five borings at location CPT -14 will be installed approximately 150 feet north- <br />northeast of CPT -9 and approximately 325 feet down -gradient of the furthest up - <br />gradient end of the former UST pit (source). <br />Note: CPT -12 & CPT -13 were moved further east from the original plan, which was <br />approved in the November 8, 2021 Regional Board Correspondence. However, due to a <br />homeless encampment in the original vicinity of the CPT -12 & CPT -13, on March 4, 2022, <br />Vera Fischer, RWQCB regulator, verbally approved moving these two boreholes to the <br />location as shown on Figure 2. <br />At each location the CPT rig will drill one boring to approximately 125 feet below ground <br />surface (bgs) and provide a CPT log. A CPT rig will also drill four (4) discrete boreholes to <br />each aquifer unit and collect a discrete groundwater sample from the desired depth. Samples <br />will be collected from the middle of the aquifer units. The depth will be refined based on the <br />initial CPT boring's log. The approximate aquifer depths are as follows: <br />• Aquifer Horizon A = <br />30 to 46 ft bgs <br />• Aquifer Horizon B = <br />50 to 56 ft bgs <br />• Aquifer Horizon C = <br />72 to 86 ft bgs <br />• Aquifer Horizon D = <br />95 to 110 ft bgs <br />After sampling, the boreholes will be backfilled to grade with neat cement and capped with <br />soil in accordance with SJCEHD requirements. <br />Traffic Control will be performed by Safe -T -Lite using the enclosed Traffic Control Plan for <br />CPT -15 & CPT -16 boreholes. <br />