SHALLOW INJECTION WELL INSTALLATION WORK PLAN <br />arcadis.com <br />2022.02.15 OCC Lathrop_Shallow Injection Well Installation Work Plan_final 4 <br />4.1 Pilot Boring and Injection Well Installation Activities <br />4.1.1 Pre-Field Activities <br />Prior to well installation activities, underground utility clearance, and permitting and property access <br />negotiations will be conducted as described below. <br />4.1.1.1 Health and Safety <br />The Site-Specific Health and Safety Plan (HASP; Arcadis 2021) outlines general health and safety <br />procedures followed at the site and will be reviewed by Arcadis field staff and the subcontractor’s field <br />staff prior to beginning field activities. General and well installation health and safety procedures will be <br />followed during field activities as outlined in the HASP. <br />4.1.1.2 Underground Utility Clearance <br />Prior to commencement of investigation activities, and in accordance with state law, Underground Service <br />Alert (USA) will be notified of the intent to conduct subsurface investigations at least 48 hours prior to <br />initiation of intrusive field tasks. The proposed well locations will be clearly marked with white paint or <br />surveyor’s flagging as required by USA. In addition, USA will notify utility owners of record within the <br />vicinity of the proposed well location. The utility owners of record, or their designated agents, will be <br />expected to clearly mark the position of their utilities on the ground surface throughout all publicly owned <br />areas designated for well installations. <br />In addition to contacting USA, a private utility locator will be contracted to assess for locations of potential <br />underground utilities (i.e., pipes, electrical conductors, fuel lines, and/or sewer lines) before intrusive work <br />is performed. The well locations will be cleared to a depth of 5 feet bgs using air-knife and/or hand- <br />digging methods to further evaluate for the presence of underground utilities. The proposed well locations <br />may be adjusted in the field based on the presence of utilities. <br />4.1.1.3 Permits <br />Well installation permits will be obtained from the San Joaquin County Environmental Health Department <br />(SJCEHD) before drilling activities begin. The pilot borings and wells will be installed in accordance with <br />the SJCEHD Well Standards (Appendix A). <br />4.1.1.4 Proposed Grouting Method and Drilling Fluid Review <br />Prior to the start of work, the C-57 licensed contractor will provide copies of all specifications and written <br />installation procedures for the proposed drilling fluid, grout, and proposed well materials to Arcadis for <br />review and approval.