6. Page FS1.1 General Tank & Line Notes #2 list the 87 tank as 15,000 but the application page 3 of  <br />8 list 20,000 gallon tank. Resubmit with clarification.  20k IS CORRECT, CHANGED NOTE  <br />a. FS1.1 & FS1.2 Map of underground tanks need clarification. Which fuel tank will be the  <br />end tank? It does not match page FS3.0 MODERN WELDING DOES NOT HAVE AN END  <br />TANK CHART, THEY SAID IT WAS THE SAME AT THE 10K,  THEY USE A 20K TANK AND  <br />INSERT A BAFFEL BETWEEN THEM.  <br />b. “Fuel Key Notes #2” Please clarify which VeederRoot will be used.   <br />7. Page FS3.0 list the 87 unleaded tank as 15,000 gal, page 3 od 8 list the 87 unleaded tank as  <br />20,000 gal. Resubmit with clarification. TANK IS 20k  SEE PAGE, 3 SEE FS3.0  <br />8. FS2.0 does not list vent sump or equipment.  <br />9. What is the longest pipe length? SEE ZONES ON FS.70 COMBINED LENGTH OF EACH ZONE IS  <br />GIVEN.  <br />10. What is the Ground Water Level? UNKNOWN, CALCS ARE FOR FULL WATER COVERAGE WE  <br />EXPECT OVER 30’ BELOW GRADE  <br />11. Where are your test ports on both ends (communication)? Vacuum Zones? ADDED TO FS7.0  <br />DETAILS  <br />12. Is there any chase piping?  Yes added to FS7.0  <br />13. There were two versions of the FS1.1  and FS1.2 sent to me. Clarify the version map that will be  <br />used.  See revised attached sheets  <br />14. Page FS4.0 Section #5 & #2 list the Concrete Slab as 6 inches but the bouncy calculation list top  <br />slab thickness as 8.00 inches. Please clarify. Revised to 8”. See detail 11/FS4.1  <br />  <br />