Traffic Impact Study Griffith Energy Storage Project <br /> EXECUTIVE SUMMARY <br /> The construction and operation of the Griffith Energy Storage Project(Project)would result in a less than <br /> significant impact to San Joaquin County Infrastructure. At peak construction, there would be <br /> approximately 60 workers and 10 to 20 trucks per day. The peak period is approximately five months and <br /> total construction is approximately twelve months, plus an additional three months of testing and <br /> commissioning. The analysis was performed with consideration for vehicle miles traveled. This resulted in <br /> impacts that are considered acceptable from both construction and operations Project-related traffic. <br /> NTETRA TECH ES-i February 2023 <br />