Stage Description Duration(Days) Week Nos, <br /> 1 Site and Substation Preparation and Grading 80 1-16. <br /> 2 Energy Storage Enclosure and Substation Installation 180 17-52 <br /> 3 Gen-Tie Line Foundation and Tower Erection 3041-46 <br /> 4 Gen-Tie Line Pulling and Stringing 3047-52 <br /> 5 Testing and Commissioning 6053-64 <br /> Equipment Daily Daily Total Haul <br /> Construction Phase Worker Vendor Truck <br /> Vehicle <br /> Equipment Type Quantity Usage Trips'cl Trips' Trips' <br /> Hours <br /> Air Compressors 4 8 <br /> Tractors/Loaders/Backhoes 2 8 <br /> Graders 2 8 <br /> Off-Highway Trucks 8 8 <br /> Rollers 2 8 <br /> Site Clearing and Rubber Tired Dozers 2 8 <br /> Preparation Rubber Tired Loaders 2 8 40 4 3,680 <br /> Skid Steer Loaders 4 8 <br /> Trenchers 2 8 <br /> Dumpers/Tenders 8 8 <br /> Generators 2 24 <br /> Generators 2 8 <br /> Air Compressors 4 8 <br /> Cranes 2 8 <br /> Excavators 4 8 <br /> Energy Storage Generator Sets 4 8 <br /> Enclosure and Substation 120 20 3,600 <br /> Installation Forklifts 2 8 <br /> Plate Compactors 2 84 <br /> Rollers 2 84 <br /> Tractors/Loaders/Backhoes 6 80 <br /> Air Compressors 2 8 <br /> Cranes 2 8 <br /> Gen-Tie Line Foundation Forklifts 2 8 <br /> and Tower Erection Generator Sets 2 24 40 4 600 <br /> Pumps 2 8 <br /> Welders 2 8 <br /> Forklifts 2 8 <br /> Gen-Tie Line Pulling and 49 4 600 <br /> Stringing Generator Sets 2 8 <br /> Tractors/Loaders/Backhoes 2 8 <br /> Testing and Off-Highway Trucks 3 8 100 0 0 <br /> Commissionin <br />