which is imperative given that Forward will deplete existing constructed airspace during <br />the winter of 201912020. <br />Based on our conversation on 19 August 2019 regarding Question 2 of your 16 August <br />2019 letter and your satisfaction with the pipe velocity calculation and the associated pipe <br />grade, the Contractor is finalizingthe subgrade preparation (i.e. bottom of clay liner) and <br />is scheduldd to start placing clay liner on 3 September 2019. Therefore, receiving an <br />approval for construction of WMU FU-19 is extremely urgent. I will follow-up on the <br />'response to Question I with a'telephone call. Alternatively, if you have any questions, <br />please call me or Don Litchfield of Forward, Inc. at 209.684.4733. <br />Sincerelj, <br />Sangeeta Lewis, P.E. <br />Principal, Lewis Engineering <br />c: Don Litchfield/ Forward. Inc. <br />Robert Mclellon, San Joaquin County, Dept of Enw Health <br />Attachment: Operation Layer Soil test results